Update - Lebanon State Airport Runway and Taxiway Surface Seal Project Starting August 3rd
Oregon Department of Aviation sent this bulletin at 07/23/2026 03:42 PM PDT7/23/2026 Update - The Lebanon State Airport Runway and Taxiway Surface Seal Project will begin August 3rd, 2026. A previous notice had the project starting on the 4th, but the contractor has requested we move it back to the 3rd. We apologize for any inconvenience.
This project will include crack seal, pavement patching, surface seal, and new pavement markings on the runway, west taxiways.

Surface Closures and Project Phasing:
The runway and west taxiways are expected to be closed for up to 4 days between 2 work areas.
The work areas are designed to keep closure impacts to a minimum. We will reopen each surface as quickly as possible.
Project Schedule:
- Project start - Monday August 3rd
- Runway Closed
- 7am Monday August 3rd - 8pm Wednesday August 5th
- Taxiway Bravo Closed
- 7am Monday August 3rd - 8pm Thursday August 6th
- Substantial Completion - 8pm Thursday August 6th
- Runway Closed
Important Operating Information
(!) When the runway is closed, fixed wing aircraft will not be able to arrive or depart at Lebanon until the runway reopens. The runway may reopen while work is being done on the taxiways. Access to the west hangars may be restricted depending on taxiway closures.
(!!) Please check NOTAMs for closure times and the most current airport surface closures. Helicopters may arrive or depart directly to/from open areas of the airport.
(!!!) As always, please remain outside of, and avoid low flight over closed work areas.