Update - Bandon Runway and Taxiway Closure 6/04/2026

New Logo

Having trouble viewing this email? View it as a Web page.

Bookmark and Share

Update - The Bandon State Airport Runway and Taxiways closure for final markings application is scheduled for Thursday June 4th.  

This work was originally planned for the fall of 2025, but it was delayed due to weather. Because this work is weather dependent, it may be rescheduled again if necessary.

Final markings application will complete the Runway and Taxiway Surface Seal Project, which was substantially completed in September 2025 and included crack seal, asphalt patch repair, surface seal, and new pavement markings on the runway and taxiways. 

Bandon

The runway, taxiway, and main apron will be closed from 8am to 6pm Thursday June 4th. 

We will work to keep the closure as short as possible, and reopen surfaces as soon as they are finished.

Important Operating Information

(!) When the runway is closed, fixed wing aircraft will not be able to arrive or depart at Bandon until the runway reopens. The runway may reopen while work is being done on the taxiways. Back-taxi may be required depending on taxiway closures. 

(!!) Please check NOTAMs for closure times and the most current airport surface closures. Helicopters may arrive or depart directly to/from open areas of the airport.

(!!!) As always, please remain outside of, and avoid low flight over closed work areas.

Thank you for your patience while we maintain the Bandon State Airport.