Interstate 74 Resurfacing Project Update
Ramp closures will be in effect this week and next for paving work
Hamilton County (Wednesday, October 7, 2026) – Ramp closures will be in place at Interstate 74 and state Route 128 during late night and overnight hours beginning tomorrow and continuing into early next week for paving operations as part of the I-74 resurfacing project.
Work will start on the ramps in the westbound direction on Thursday and Friday, and then crews will shift to the eastbound ramps on Sunday and Monday. The schedule will be as follows, and during periods of closure, motorists may use the Harrison Avenue interchange to detour.
Thursday, October 8:
- Closure of the ramp from westbound I-74 to S.R. 128, from 10 p.m. to 5 a.m. Friday.
Friday, October 9:
- Closure of the ramp from S.R. 128 to I-74 West, from 10 p.m. to 5 a.m. Saturday.
Sunday, October 12:
- Closure of the ramp from eastbound I-74 to S.R. 128, from 10 p.m. to 5 a.m. Monday.
Monday, October 13:
- Closure of the ramp from S.R. 128 to I-74 East, from 10 p.m. to 5 a.m. Tuesday.
Project Overview
The I-74 resurfacing project extends from just west of the S.R. 128 interchange at Miamitown to the Rybolt Road/Harrison Avenue interchange. In addition to paving the interstate, the project includes minor bridge work such as deck sealing, expansion joint repairs, and drilling of fatigue cracks on the structures within the project limits, as well as on the West and New Haven Road bridges that carry traffic over I-74.
Barrett Paving Materials, Inc. was awarded a contract in the amount of $9.58 million to complete the project, and while paving is anticipated to begin by mid-September, all work is scheduled to be completed in early November.
###
For more information contact: ODOT District 8 Public Information 513-933-6517 - or - 513-933-6534
Know Before You Go!
For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.
|
|