Hamilton County: Linn Street Reconstruction Project

Having trouble viewing this email? View it as a Web page.

Zephyr-Ohio-White

Linn Street Reconstruction Project Update

Northbound I-75 reopens ahead of schedule; I-75 South remains closed going into the overnight


Hamilton County
(Sunday, September 27, 2026) –
Good news for motorists traveling north on Interstate 75 into Ohio tonight, as the northbound lanes have been reopened ahead of schedule following beam installation for the Linn Street Bridge Replacement and Reconstruction project.

The southbound lanes of I-75 will remain closed heading into the overnight hours for crews to finish work on the beams and implement a traffic switch on I-75 South to accommodate construction for the Brent Spence Bridge Corridor project; however, it is expected that all lanes will be open to traffic ahead of the morning rush hour. 

Until I-75 South is open to traffic, thru-traffic motorists can follow the signed detour by way of S.R. 562/Norwood Lateral and I-71 to reconnect with I-75 at the approach to the Brent Spence Bridge.

Locally, drivers can also take the Freeman Avenue exit (Exit 1F) and make their way to the west side or downtown Cincinnati by way of Freeman and either Eighth Street, Sixth Street, Linn and Third, or Mehring Way.

Linn Street NB beams

 

Project At A Glance

The Linn Street Reconstruction Project, which is part of the broader Brent Spence Bridge Corridor and the improvements to the Ohio Phases 1 and 2 segments, includes replacing and reconstructing the bridge between W. 8th and W. Court streets and reconfiguring it to two, 10-foot driving lanes, with bike lanes and sidewalks on each side. The project will also include some minor reconfiguring of W. Court Street and Winchell Avenue, as well as replacement of the pedestrian bridge over Winchell.

Great Lakes Construction Company was awarded a contract in the amount of $46.7 million to undertake the Linn Street project, and while Linn Street is anticipated to be reopened to traffic in the fall of 2027, all work is scheduled to be completed in late spring of 2029.

 

###

 

For more information contact: 
ODOT District 8 Public Information