ODOT kicking off another record construction season

Nearly 1,000 projects valued at $3.4 billion statewide

CLEVELAND – Spring in Ohio means orange barrels and renewed investment in Ohio’s infrastructure. The Ohio Department of Transportation (ODOT) is kicking off a record-breaking $3.4 billion construction season statewide.

The 2026 construction season includes a total of 977 new projects. This year, 739 bridges and approximately 4,562 miles of roadway, equivalent to driving from Columbus to San Diego, California, and back, are set to be improved. There are 36 major projects with a value over $10 million. Eighty cents of every dollar invested this year will go directly to preservation of existing roads and bridges.

This construction season will also include the start of 174 safety projects. Ohio continues to spend more per capita than any other state when it comes to roadway safety.

“As a state that makes and moves things, we must have a safe transportation system that is well maintained,” said Governor Mike DeWine. “As they do each year, our ODOT teams will be making enhancements to Ohio’s roadways to better protect everyone traveling on them.”

Since the beginning of the DeWine Administration in 2019, ODOT has invested $15.5 billion into 6,067 projects across the state.

“This record-setting construction season is a testament to ODOT’s focus on building a more resilient transportation system and saving lives,” said ODOT Director Pamela Boratyn. “This investment positions Ohio as the heart of the nation’s supply chain and continues to fuel the state’s economic engine."

NORTHEAST OHIO PROJECT HIGHLIGHTS

Officials in northeast Ohio announced 175 new projects for 2026 valued at $891 million in 17 counties. A total of 231 projects will be active this construction season, which includes new and carryover projects from previous construction seasons.

A few of the major projects with a value over $10 million that will be active this summer include:

  • Cuyahoga County – I-90 between E. 9th and Carnegie Ave.
    The $328 million project includes replacing the pavement and five bridges. Estimated completion summer 2032.
  • Cuyahoga County – I-90 between Hillard and West boulevards
    The $173 million project began in 2025 and will continue through fall 2028 rebuilding the pavement in this corridor.
  • Erie County - U.S. 6 Connectivity Corridor
    The $27 million project will increase the efficiency and operation of the U.S. 6 corridor from Cedar Point Drive through the State Route 2 interchange with Rye Beach Road. Work is expected to be completed by the spring of 2029.
  • Lorain County – I-90 between the Ohio Turnpike and SR 611
    The $115.8 million major reconstruction project includes complete pavement replacement and adding one lane in each direction. Work began in spring 2025 and is expected to be complete summer 2028.
  • Mahoning County – I-680 between SR 193 and South Ave.
    The $59.5 million project includes replacing the pavement. Work began this spring and is estimated to be completed in October 2027.
  • Summit County - SR 8 hi-level bridge replacement
    The $157.6 million project includes replacement of the SR 8 hi-level bridge over the Cuyahoga River Valley with two new structures and minor re-alignment of SR 8 and the addition of a new auxiliary lane in each direction of SR 8 between Glenwood Ave. and Perkins St. Estimated completion is set for the summer of 2028.
  • Summit County – I-77 between Ghent and Everett roads
    The $52 million project began in the spring of 2025 and is widening I-77 from two to three lanes in each direction and work on 12 bridges. Work is expected to be complete in summer 2027.

To view a complete list of projects in each county, check out the online ODOT Construction Guide. 

You can stay up to date on construction across the state by signing up for weekly bulletins or visiting the projects page on the ODOT website. You can also see where work might impact your commute or trip at OHGO.com.  

WORK ZONE SAFETY 

According to the Ohio State Highway Patrol, there were 4,435 work zone crashes in Ohio last year with 34% of those crashes occurring with workers present. Sadly, 21 people were killed in 17 deadly work zone crashes. Another 96 work zone crashes resulted in serious injuries. 

Speeding and following too closely continue to be the top factors in work zone crashes. Troopers wrote 7,019 citations for speeding in work zones with 36% for speeds more than 20 miles per hour above the posted speed limit.

On February 28, a vehicle drove onto a closed section of I-70 in downtown Columbus and struck Jordan Thomas, an employee of Kokosing Construction. Thomas, 25, died from his injuries. The driver of the vehicle fled the scene and still has not been found. A reward of $110,000 has been offered for information leading to their arrest. Anyone with information about the hit-and-run is asked to contact Central Ohio Crime Stoppers at 614-461-8477. Tips can be reported anonymously.

 

***