Greene County: U.S. 35 Pavement Rehabilitation Project Update

Having trouble viewing this email? View it as a Web page.

Zephyr-Ohio-White

U.S. 35 Pavement Rehabilitation Project Update

Ramp closures at U.S. 35/I-675 interchange this week

Greene County (Sunday, September 14, 2025) – A series of ramp closures will be in effect this week on U.S. Route 35 for paving work as part of the ongoing bridge and pavement rehabilitation project.

On Tuesday, September 16, the ramp from eastbound U.S. 35 to I-675 North and South will be closed beginning at 10 p.m., and the closure will remain in effect until 5 a.m. Wednesday. While the ramp is closed, motorists may detour via the N. Fairfield Road interchange and U.S. 35 West to I-675.

Then on Wednesday and Thursday, September 17 and 18, operations will flip to the westbound side of U.S. 35, where the ramp to I-675 will be closed each night at 10 p.m. Restrictions will be lifted by 5 a.m. the following day, but during periods of closure motorists may use the Woodman Drive interchange and U.S. 35 East to I-675.

Finally, on Friday, September 19, the ramps from eastbound U.S. 35 to Research Boulevard and to/from N. Fairfield Road, will be closed from 10 p.m. to 5 a.m. Saturday. Motorists may detour by way of the signalized permitted U-Turn to U.S. 35 West.

The total project includes removing the concrete pavement, completing sub-grade repairs and resurfacing U.S. 35 from the Montgomery County line to the structure over Grange Hall Road, immediately east of the S.R. 835/N. Fairfield Road interchange in the city of Beavercreek. The project also includes minor bridge repairs and construction of a median inlet.

Westbound U.S. 35 traffic is currently reduced to one lane, and the C-D lane is closed. In addition, the ramp from I-675 North to U.S. 35 West is closed through early October, and traffic is being routed by way of U.S. 35 and the S.R. 835/N. Fairfield Road interchange to U.S. 35 West. 

Eastbound U.S. 35 is being maintained in two lanes; however, intermittent evening and overnight restrictions may in place, resulting in single-lane closures within the work zone. 

The John R. Jurgensen Company was awarded a contract in the amount of approximately $6.59 million to complete the project, and all work is scheduled to be completed in the fall of 2026.

###

For more information contact: 
District 8 Public Information
513-933-6517 - or - 513-933-6534


OHGO.com logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.


ORANGE move over logo August 2023