Interstate 75/Mill Creek Expressway Project - Phase 8
|
|
|
Hamilton County (Monday, May 5, 2025) – The following restriction will be in place this week as part of the Interstate 75/Mill Creek Expressway - Phase 8 project.
Monday, May 5:
- Closure of the I-75 contraflow lane, from 8 p.m. to 6 a.m. Tuesday for excavation work.
- Closure of the ramp from I-75 South to S.R. 562 East, from 9 p.m. to 6 a.m. Tuesday for installation of portable concrete barrier (PCB).
Tuesday, May 6:
- Closure of the I-75 contraflow lane, from 8 p.m. to 6 a.m. Wednesday for equipment mobilization.
- Single-lane closure on S.R. 562 West, from 8 p.m. to 6 a.m. Wednesday.
- Closure of the ramps from I-75 South and North to S.R. 562 East, from 10 p.m. to 6 a.m. Wednesday, for pavement repairs.
Wednesday, May 7:
- Single-lane closure on S.R. 562 West, from 8 p.m. to 6 a.m. Thursday.
- Closure of the ramp from I-75 South to S.R. 562 East, from 8 p.m. to 6 a.m. Thursday.
Thursday, May 8:
- Closure of the I-75 contraflow lane, from 8 p.m. to 6 a.m. Friday for equipment mobilization.
- Single-lane closure on S.R. 562 West, from 8 p.m. to 6 a.m. Friday for PCB installation
- Closure of the ramp from I-75 North to S.R. 562 East, from 8 p.m. to approximately midnight.
- Closure of the ramp from I-75 South to S.R. 562 East, from approximately 10 p.m. to 6 a.m. Friday. (The closure time is estimated, and the ramp will not be closed until after the ramp from northbound I-75 to S.R. 562 has been reopened.)
###
For more information contact: Kathleen Fuller, 513-933-6517 Liz Lyons, 513-933-6534
Know Before You Go!
For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.
|
|
|