WASHINGTON COUNTY: Weekly Construction Update

Having trouble viewing this email? View it as a Web page.

Wordmark
 

Contact: District 10 public information office

740-568-3904, Ashley.Rittenhouse@dot.ohio.gov

WASHINGTON COUNTY: Weekly Construction Update

WEEK OF OCTOBER 3, 2022

MARIETTA, Ohio (Thursday, September 29, 2022) - The following construction projects are anticipated to affect highways in Washington County. All outlined work is weather permitting. Click on each route to see its location at OHGO.com.


7

STATE ROUTE 7 PROJECTS

SR 7 Resurfacing - A resurfacing project is taking place on SR 7, between Captain D Seeley MIA Drive and Commerce Drive. Lane closures are in place. Estimated completion: September 30, 2022

SR 7 Rockfall Repair - A rockfall repair project is taking place on SR 7, between SR 807 and Dana Road (County Road 244). One lane is closed. Traffic is being maintained with temporary signals, except during blasting operations when it will be held up to 15 minutes at a time. Estimated completion: October 31, 2022

SR 7 Culvert Replacement - A culvert replacement project is taking place on SR 7, between Sheets Run Road (County Road 47) and Commerce Drive (Township Road 1493). One lane is closed. Traffic is being maintained with temporary signals. Estimated completion: November 18, 2022


SR 618 Resurfacing - A resurfacing project is taking place on SR 618, between Main Street and Drag Strip Road. Lane closures are in place. Estimated completion: November 1, 2022

SR 60/SR 821 Resurfacing - A resurfacing project is taking place on SR 60, between Marion Street and SR 821. Lane closures are in place from 9 p.m-5 a.m., Monday through Friday. Estimated completion: November 15, 2022

SR 676 Resurfacing - A resurfacing project is taking place on SR 676, between SR 339 and the Marietta Corporation Limit (Gates Avenue). One lane is closed. Traffic is being maintained by flaggers. Estimated completion: November 15, 2022

City of Marietta Start Westward Project - Phase 1 of the City of Marietta's Start Westward project is currently underway, between Front/Wooster and Front/Putnam Streets. Improvements are planned for the sidewalk/curb, street lighting, and Muskingum Park drive access. Two-way traffic will be maintained at all times; however, street parking will be unavailable. Estimated completion: December 1, 2022


MOVE OVER LOGO GOV APPROVED

OHGO.com logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.