WOOD COUNTY: Highway Construction Update, August 25

Having trouble viewing this email? View it as a Web page.

Wordmark
 

For Immediate Release

Thursday, August 25, 2022

 

Updates are highlighted in bold and underlined

 

WOOD COUNTY: Highway Construction Update


I-75_large

Project ID: 93592, 93594

Interstate 75, between Buck Road and Monroe Street, Toledo/Rossford/Northwood, will be two lanes in each direction for major reconstruction. Lane restrictions and overnight ramp closures possible. Estimated completion: Fall 2023.

New Announcements/Upcoming Impacts

  • Nebraska Ave. over I-75 is now open as of Aug. 22
  • Ramp from northbound/inbound AW Trail to northbound I-75 is open as of Aug. 24.
  • I-75, between Miami St. and South Ave., may experience overnight rolling roadblocks and short-term delays for bridge work through August, 9 p.m.-6 a.m.

Continuing Work

  • South Ave., between northbound South Ave. ramps and southbound South Ave. ramps, is closed for reconstruction through Friday, September 2. Closure timeline was affected due to utility delays.
  • Southbound/outbound State Route 25/Anthony Wayne Trail will be reduced to one lane between I-75 and Collingwood Blvd. for reconstruction of AW Trail through August.
    • Outbound Anthony Wayne Trail and entrance/exit ramps to IR 75 will be paved Wednesday-Friday nights, Aug. 24-26.
    • Nightly closures of the outbound Anthony Wayne Trail will occur the remainder of this week.
    • All of outbound Anthony Wayne Trail and ramps are expected to be complete by Aug. 26.
  • Ramp from northbound/inbound Anthony Wayne Trail to northbound I-75 is open.
  • Northbound I-75 exit to Miami St. (Exit 199) is closed for reconstruction through October. Detour: Northbound I-75 to Collingwood Blvd. (Exit 201A) to southbound I-75 to Miami St. (Exit 199)
  • Miami St. on ramp to northbound I-75 is closed for reconstruction through October. Detour: Southbound I-75 to Wales Rd. to northbound I-75.

I-280_small

Front Street entrance ramp to Interstate 280 southbound will be closed Aug. 25-26 for removal of trees. Motorists may determine an alternate route as no official detour will be posted.


I-280_small

Project ID: 110514

Walbridge Rd. over I-280, Walbridge, will experience lane restrictions for resurfacing through mid September.


I-280_small

Project ID: 113685

Interstate 280, between SR 51 and SR 2, Northwood/Oregon, may experience lane restrictions for pavement repairs through August.


US 23_large

Project ID: 102922

U.S. Route 23, between Township Road 49 and US 6, Risingsun, will experience lane restrictions for resurfacing through August.


SR18

Project ID: Maintenance

State Route 18, between Range Line Rd. and Liberty Hi Rd., Weston, closed Aug. 22 for pavement repairs through Thursday, Aug. 25. Detour: SR 235 to SR 613 to I-75.


SR 25

Project ID: 92133

State Route 25, between Cygnet Rd. and US 6, Bowling Green/Portage, will experience lane restrictions and closures for roadway reconstruction through summer 2023.

The following closures will begin Thursday, Aug. 25 and remain in place for 90 days. Access to businesses will be maintained:

  • SR 25 from just north of Mermill Road  to just south of Arlington Woods, including the intersection at Mermill Road.
    • Arlington Woods residents may detour to the south.
  • SR 25 between the Wayne Homes, Schumacher Homes, and K Hovnanian Homes location to approximately one mile south of Bays Road, including the intersection with Jerry City Road.
    • Business traffic will be maintained from the south via temporary pavement.

Work that will continue:

  • SR 25, between Cygnet Rd. and Portage, is closed for storm sewer work and road reconstruction through October. Residential access will be maintained. Detour: I-75 and US 6.
  • Bays Rd. at SR 25 will close for intersection reconstruction through August.

65

Project ID: Permit

State Route 65, between Roachton Rd. and Hull Prairie Rd., Perrysburg Twp., closed Aug. 15 for pump station replacement  through mid-November. Detour: Roachton Rd. to Hull Prairie Rd. to SR 65.


65

Project ID: 95796

State Route 65, between SR 235 and Henry County line, will experience lane restrictions for resurfacing through September.


SR 235

Project ID: 102925

State Route 235, between Bays Rd. and Jerry City Rd., Milton Twp./Custar, is closed for two bridge replacements through September. Detour: SR 235 to SR 18 to SR 65 to SR 281 to SR 235.


SR 281

Project ID: 94340

State Route 281, between SR 235 and I-75, Wingston/Rudolph, will experience lane restrictions for resurfacing through September.


Various routes district-wide will experience lane restrictions for routine guardrail, lighting, and pavement markings and maintenance throughout the year.


**All work is weather permitting.**

 

For more information contact: 

The District Two Public Information Office at

(419) 373-4428
or email D02.PIO@dot.ohio.gov


OHGO.com logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.


The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.