CLERMONT COUNTY: Weekly Construction Update
Through the week ending July 2, 2022: The following traffic advisory includes restrictions on the state highway system in Clermont County. All work will be contingent upon the weather. For construction information and statewide information regarding road conditions, visit ODOT on the web at www.Ohgo.com.
 |
|
CONTINUING IMPACTS
Interstate 275 Cable Installation - Installation of fiber optic cable and CCTV cameras at multiple locations along the corridor, including between the U.S. 22/Montgomery Road and S.R. 28 interchanges and between the S.R. 32 and U.S. 52 interchanges in Clermont County. Traffic will be maintained through the various work zones. All work is scheduled to be complete in early summer 2022
|
 |
|
S.R. 32 Interchange/Expansion - Construction of an interchange at the intersection of S.R. 32 and Bach Buxton Road/Elick Lane and widening of S.R. 32 West between the new interchange and Glen Este-Withamsville (GEW) Road. Intermittent lane restrictions will be in place on the mainline, as well as restrictions on secondary routes, including the following:
- Marian Drive is closed between Elick Lane/Bach Buxton Road and Eastgate Woods. This is a temporary closure during construction, and the route will reopen when the new interchange opens. Access is being maintained to businesses off Marian Drive.
S.R. 32 RCUT Installation - At the intersection with Bauer Road. Crews are completing paving operations and other finishing work. Traffic will be maintained through the work zone; however, lane restrictions may be in effect during the evening and overnight hours. The entire project is scheduled to be completed in the spring of 2022.
|
NEW IMPACTS
S.R. 28 Intersection Improvement/Bridge Repair - Construction of a continuous flow lane from Business S.R. 28 to I-275 North and bridge rehabilitation on the S.R. 28 structure over I-275. Intermittent lane restrictions will be in effect on S.R. 28 during the evening and overnight hours. The entire project is scheduled for completion in the summer of 2023.
S.R. 126 Resurfacing - Between Milford and Loveland Madeira Road near Indian Hill. Single-lane closures will be in effect from 7 a.m. to 7 p.m., and traffic will be maintained by flaggers during hours of operation. The project is scheduled to be completed in early fall of 2022.
S.R. 132 Culvert Replacement - Immediately north of Cedarville Road, between S.R. 131 and S.R. 28. S.R. 132 will be closed July 5-26, and traffic will be detoured by way of S.R. 131, U.S. 50, S.R. 450, I-275 and S.R. 28. All work associated with the project is scheduled to be completed in early fall.
S.R. 222 Bridge Replacement - Between S.R. 756 and Caldwell Road. S.R. 222 is closed east of Mulberry Street and north of the village of Felicity for 20 days effective Monday, June 6. Motorists will be detoured via S.R. 743 and S.R. 756. All work is scheduled to be completed by early fall.
S.R. 450 Resurfacing - On S.R. 450, between U.S. 50 and the ramps to Milford Parkway, adjacent to I-275. Intermittent lane restrictions will be in effect through the work zone. Construction is scheduled tentatively to begin the week of July 5, and all work is scheduled to be complete in early fall of 2022.
CONTINUING IMPACTS
S.R. 125 Resurfacing - Between Amelia-Olive Branch Road and S.R. 132. Nightly lane closures will be in effect from 7 p.m. to 6 a.m. the following day, and a minimum of one lane of traffic will be maintained in each direction. All work is scheduled to be completed in early fall of 2022.
S.R. 756 Culvert Replacement/Resurfacing - Between S.R. 232 and the Brown County line. Construction also includes pavement repairs and replacing three culverts within the project limits. Restrictions will be in effect for paving operations between S.R. 133 and the Brown County line. Traffic will be maintained by flaggers. The project is scheduled to be completed in the summer of 2022.
U.S. 50 Resurfacing - Between S.R. 222 and Owensville. Crews will return to complete final paving and pavement markings, and traffic will be maintained by flaggers during hours of operation. The entire project is scheduled to be completed in the spring of 2022.
###
For more information contact: Kathleen Fuller, 513-933-6517 Liz Lyons, 513-933-6534