MIAMI COUNTY: Weekly Construction Update

Having trouble viewing this email? View it as a Web page.

Wordmark
 

Contact: District 7 Public Information Office

937-497-6959, d07.pio@dot.ohio.gov

MIAMI COUNTY: Weekly Construction Update

WEEK OF May 31, 2021

SIDNEY, Ohio (Friday, May 28, 2021) – The following construction projects are anticipated to affect state highways in Miami County next week. All outlined work is weather permitting. Visit the ODOT website and OHGO.com for travel updates.


I-75_large

NEW IMPACTS:

Interstate 75 Resurfacing – Expect lane restrictions on I-75, in each direction, between S.R. 41 and U.S. 36, on Wednesday, June 2 through Sunday, July 31, from 7:00 p.m. – 6:00 a.m. Crews will be performing an asphalt overlay. One 12’ lane will be maintained in the work zone.

CONTINUING IMPACTS:

Interstate 75 Maintenance – Expect lane closures on I-75, in each direction, between U.S. 36 and County Road 25A (Piqua Exit), on Monday, May 17 through Friday, June 11, from 9:00 a.m. – 2:00 p.m. Crews will be performing asphalt repairs. One of two lanes of I-75 will be maintained without lane restrictions.

UPCOMING IMPACTS:

Interstate 75 Ramp Resurfacing the I-75 southbound entrance ramp from S.R. 41 southbound will close, two nights, Tuesday, June 29 and Wednesday, June 30 from 7:00 p.m. – 6:00 a.m. The contractor will be resurfacing I-75 southbound ramp.

  • Detour: SR-41 to I-75 NB take CR-25A (Exit 78) turn left onto CR-25A. Turn left onto I-75 southbound

Interstate 75 Bridge Maintenance – Expect lane closures on I-75, in each direction, between Country Road 25A (Exit 78) and U.S. 36 (Piqua Exit), on Monday, June 7, from 9:00 a.m. – 2:00 p.m. Crews will be performing bridge inspections. One of two lanes of I-75 will be maintained without lane restrictions.


36

CONTINUING IMPACTS:

U.S. 36 Resurfacing – Expect lane restrictions on U.S. 36, in each direction, between S.R. 48 and Robert M Davis Parkway, on Monday, April 26 through Saturday, July 31 from 7:00 a.m. – 6:00 p.m. One 12’ lane will be maintained in the work zone.

UPCOMING IMPACTS:

U.S. 36 Utility Repairs – Expect U.S. 36 to close at S.R. 48, on Monday, June 7 through Friday, July 9. The contractor will be performing utility extensions. The Village of Covington is handling this project.

  • U.S. 36 Detour - S.R. 721 to S.R. 185

571

State Route 571 Road Reconstruction –S.R. 571 will close  in Tipp City, in each direction, between First Street and S.R. 202, on Monday, May 3 at 7:00 a.m. through Sunday, August 1, at 5:00 p.m. The Contractor will be reconstructing the road and upgrading the sidewalks. The Great Miami River Recreation Trail will be closed between Parkwood Drive and Kyle Park Drive.

•    S.R. 571 (EB) Detour: I-75 SB to I-70 EB to S.R. 202 To S.R. 571
•    S.R. 571 (WB) Detour: S.R. 202 SB to I-70 WB to I-75 NB to S.R. 571


CONTINUING IMPACTS:

State Route 41 Resurfacing– Expect lane restrictions on S.R. 41, in each direction, between S.R. 48 and I-75, on Monday, May 10 through Saturday, July 31, from 7:00 a.m. – 6:00 p.m. One 12’ lane will be maintained in the work zone.

State Route 41 Utility Project– State Route 41 will close in Covington, Ohio, between Pearl Street and U.S. 36 on Friday, April 2 at 7:00 a.m. through Wednesday, June 30 at 5:00 p.m. The contractor is performing a utility upgrade. This a Village of Covington project.

•    Detour: I-75 to U.S. 36


State Route 48 Utility Project– State Route 48 will close in Covington, Ohio, between Dodds Street and U.S. 36 on Friday, April 2 at 7:00 a.m. through Wednesday, June 30 at 5:00 p.m. The contractor is performing a utility upgrade. This a Village of Covington project.

  • Detour: S.R. 718 to S.R. 721 to U.S. 36

State Route 201 Resurfacing – Expect lane restrictions on S.R. 201 in Elizabeth Township, in each direction, between S.R. 41 and S.R. 55, on Monday, May 10 through Thursday, July 1, from 7:00 a.m. – 6:00 p.m. Flaggers will be helping maintain traffic in the work zone.


UPCOMING IMPACTS:

County Road 25A Lane Addition - Expect lane closures on County Road 25A, in each direction, between S.R. 571 and I-75, on Monday, June 7 through Friday, October 15. The contractor will be adding a center turn lane. Traffic will be shifted onto the westside of County 25A.