For Immediate Release
Friday, May 7, 2021
Updates are highlighted in bold and underlined
WOOD COUNTY: Highway Construction Update
 |
|
Interstate 75 widening and reconstruction – I-75 between Buck Road and Monroe Street, Toledo/Rossford/Northwood, will be two lanes in each direction for major reconstruction. Lane restrictions and overnight ramp closures possible. Estimated completion: Fall 2023.
New Announcements/Upcoming Impacts
-
Eastern Ave. and Western Ave., between Broadway St. and I-75, will experience closures for drainage and pavement reconstruction. Closures begin Monday, May 10. Flyers will be posted and provided to residents in the impacted area with a schedule of ongoing closures.
Continuing Work
-
Ramp from southbound I-75 to southbound/outbound SR 25/Anthony Wayne Trail (exit 201) is closed for ramp tie-in through early May.
- Detour: Southbound I-75 to Washington St. (Exit 202A) to Washington St. to southbound SR 25/AW Trail
-
Miami St. on-ramp to southbound I-75 will be closed for ramp construction through mid-July. Detour: Miami St. to Oregon Rd. to Wales Rd. to southbound I-75
-
South Avenue entrance ramp to southbound I-75 is closed through summer 2021.
-
Detour: Northbound I-75 to Detroit Avenue back to I-75 southbound
-
Inbound SR 25/AW Trail near Nebraska Avenue will be reduced to one lane through fall 2021.
-
Southbound/outbound State Route 25/Anthony Wayne Trail will be reduced to one 10-foot lane between I-75 and City Park for reconstruction of Collingwood on-ramp and AW Trail through fall 2021.
-
Nebraska Avenue is closed over I-75 between Division Street and Erie Street for bridge replacement through July 2022.
-
Detour: Erie Street to Collingwood Boulevard to Nebraska Avenue
-
Ramp from northbound/inbound Anthony Wayne Trail to northbound I-75 is closed for ramp reconfiguration through summer 2022.
-
Detour: Anthony Wayne Trail to Washington Street to northbound I-75.
-
Ramp from southbound/outbound Anthony Wayne Trail to southbound I-75 is closed for ramp reconfiguration through summer 2022.
-
Detour: Washington Street to Dorr Street to Collingwood Boulevard to southbound I-75.
|
 |
|
*New*
Interstate 75, between US 6 and Poe Road, Bowling Green, may experience lane restrictions for falsework installation in preparation for projects on Poe Rd. and Gypsy Lane Rd., beginning Monday, May 10. Additional project details will be announced.
|
 |
|
*New*
Interstate 280, between Wales Rd. and Curtice Rd., Northwood, will experience lane restrictions for overhead bridge inspections on Wednesday, May 12 and Thursday, May 13.
|
 |
|
U.S. Route 6, between Van Tassel Road and Range Line Road, Weston, will experience lane restrictions for pavement widening and drainage work near SR 235. Estimated completion: mid-May. |
*New*
State Route 199, between US 6 and Elm St., West Millgrove, may experience lane restrictions for microsurfacing beginning Monday, May 24. Estimated completion: September 1.
State Route 235, between Euler Road and Willow Road, Weston, will be closed for pavement widening and drainage work beginning Tuesday, June 1. Estimated completion: mid-May. Detour: SR 235 to SR 65 to SR 281 to SR 235
State Route 795 at Lemoyne Road, Millbury, may experience lane restrictions for signal replacement. Estimated completion: June.
Various routes district-wide will experience lane restrictions for routine guardrail, lighting, and pavement markings and maintenance throughout the year.
**All work is weather permitting.**
For more information contact:
The District Two Public Information Office at
(419) 373-4428 or email D02.PIO@dot.ohio.gov
Know Before You Go!
For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.
|
The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.
|