HAMILTON COUNTY: Weekly Construction Update

Having trouble viewing this email? View it as a Web page.

Wordmark
 

HAMILTON COUNTY: Weekly Construction Update

Through the week ending October 3, 2020: The following traffic advisory includes restrictions on the state highway system in Hamilton County. All work will be contingent upon the weather. For construction information and statewide information regarding road conditions, visit ODOT on the web at www.Ohgo.com.

 


I-71_Small

INTERSTATE 71 CONSTRUCTION

 

I-71 Major Rehabilitation  - Widening to three lanes between S.R. 126 (Ronald Reagan Cross-County Highway) and S.R. 562 (Norwood Lateral), as well as bridge work at multiple structures and removing the Ridge Road exit and adding an exit to Kennedy Avenue on northbound I-71. Various lane restrictions will be in effect during nighttime hours for pavement work. The entire project is scheduled for completion in the summer of 2021.  

I-71 NEW IMPACTS

Red Bank Road is reduced to one lane between Big Chief Drive and Ehrling Road. The single-lane restriction will be in effect through late September, and traffic will be maintained with temporary signals. 

I-71 North traffic is shifted to the west (left) side of the interstate from just north of Red Bank Road to the Kenwood Road interchange, and the off-ramp from I-71 North to Stewart Road is closed through late October. Traffic will be detoured by way of Kenwood Road, Euclid Road and Stewart Road.


I-75_large

INTERSTATE 75 CONSTRUCTION

 

I-75/Thru the Valley Major Rehabilitation  - Addition of a fourth lane from Shepherd Lane to Glendale-Milford Road, as well as reconstructing the Shepherd Lane interchange and realigning Neumann Way. Various lane restrictions will be in effect through the construction zone, and currently the Construction is scheduled to be completed in the late fall of 2020 or early winter of 2021.

I-75/Mill Creek Expressway Major Rehabilitation  - Major rehabilitation project at the I-74/75 interchange to widen and resurface I-75 between Paddock Road and the Western Hills Viaduct and reconfigure the interchange. Construction also includes interchange improvements at Hopple Street, I-74, Mitchell Avenue, Norwood Lateral and Paddock Road. Various lane closures will be in effect through the construction zone. The project is scheduled to be completed in the fall of 2022.

I-75 North/Kemper Road Bridge Rehabilitation - On I-75 at Kemper Road. Intermittent single and double-lane closures from the Sharon Road interchange through the overpass at Kemper Road during overnight hours on weekends as needed.


I-275_small

INTERSTATE 275 CONSTRUCTION

 

I-275 Bridge Rehabilitation and Resurfacing  - Between the Four Mile Road interchange to the south end of the Combs Hehl (Ohio River) Bridge in Kentucky. Various lane and ramp closures will be in effect through the construction zone. All work is anticipated to be completed by early fall of 2020.

 


CONTINUING IMPACTS

C.R. 251 (Galbraith Road) Pavement Repair/Storm Sewer Improvement - At the intersection of Galbraith and Blue Ash roads. Traffic is being maintained through the work zone; however, Galbraith Road will be subject to closure, and traffic will be detoured using Blue Ash Road, Matson Avenue and Beech Avenue. A schedule to close Galbraith has yet to be determined. The project is scheduled for completion in Summer 2021.

S.R. 125 Resurfacing - Between Voll Street and the Clermont County line in Anderson Township. Traffic will be maintained in a minimum of one lane in each direction. All work is scheduled to be completed in the fall of 2020.

S.R. 126 Cable Rail Installation - Installation of median cable barrier rail between I-75 and I-275. Nightly lane closures between 7 p.m. and 6 a.m. Traffic will be maintained in a minimum of one in either direction during installation.

U.S. 22/S.R. 126 Roundabout  - At the intersection of U.S. 22 (Montgomery Road) and S.R. 126 (Ronald Reagan Cross-County Highway) for the Montgomery Quarter Development project. Traffic is being maintained in a minimum of one lane on Montgomery Road; however, intermittent lane restrictions and closures may be in effect at the interchange ramps to and from Montgomery Road. The project is scheduled for completion in Summer 2021.

U.S. 27 Bridge Repair - On Colerain Avenue at the I-275 overpass. Single-lane restrictions in the north and southbound direction are tentatively scheduled to be in effect from 8 p.m. Friday, Sept. 25, to 5 a.m. Monday, Sept. 28. Motorists may encounter intermittent periods of delay during hours of operation, and all work will be contingent upon the weather.

U.S. 50 Resurfacing - Between Homewood Road and the western corporation limit of Terrace Park. Single-lane restrictions will be in effect in either direction, and traffic will be maintained by law enforcement officers, barrels and/or flaggers as needed. The project is scheduled for completion in early fall of 2020.


NEW IMPACTS

I-275_small

I-275 Bridge Maintenance - Single-lane closure on I-275 North over Loveland-Madeira Road from 8 p.m. Monday, Sept. 28, to 6 a.m. Tuesday, Sept. 29, while crews place portable concrete barrier along the shoulder for upcoming bridge maintenance at the overpass. Traffic will be maintained by arrow boards and/or barrels.

S.R. 129 Noise Barrier Wall Repair - At the I-75 interchange. Traffic will be maintained with arrow boards and/or barrels.

S.R. 562/I-71 Catch Basin Repairs - At the I-71/S.R. 562 (Norwood Lateral) interchange ramp. Traffic will be maintained with arrow boards and/or barrels.

Interstate Maintenance - Mowing, sweeping, berming, drainage work and cable barrier repair at various locations along I-71, I-74, I-75 and I-275 throughout the county. Single-lane closures will be in effect as needed, and traffic will be maintained by arrow boards.

###

For more information contact: 
Kathleen Fuller, 513-933-6517
Liz Lyons, 513-933-6534