For the Week of May 4

ASHLAND COUNTY
State Route 3
SR 3, from the Village of Loudonville to the City of Wooster, will be reduced to one lane of traffic for a resurfacing project. Traffic will be maintained by flaggers. The project is expected to be complete September 2020. 

Interstate 71
I-71, just south of the US 250 interchange, will have daytime shoulder closures only as needed to complete culvert repairs. The project is expected to be complete October 2020.

 

 

CRAWFORD COUNTY
State Route 4
State Route 4, at the intersection of SR 4 and Irving Street, will be reduced to one lane for signal work. Traffic will be maintained by flaggers. The project is expected to be complete May 2020; however, all work is weather dependent and is subject to change. 

State Route 19
SR 19, from Evans Avenue to the City of Bucyrus corporation limits, will be reduced to one lane of traffic for a resurfacing project. Traffic will be maintained by flaggers. The project is expected to be complete July 2020. 

State Route 19: Resurfacing
SR 19, from Carey Road (CR 27) to SR 4, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers. The project is expected to be complete September 2020; however, all work is weather dependent and is subject to change. 

US Route 30
US 30 eastbound and westbound, from just east of SR 98 to Old Lincoln Way, will have single lane closures for bridge sealing work on structures on/over US 30. The project is expected to be complete August 2020. 

State Route 97
SR 97, between Millsboro Road to the Morrow County line, will be reduced to one lane for a resurfacing project. Traffic will be maintained by flaggers. The project is expected to be complete July 2020. 

State Route 309/61 – City of Galion
SR 309/61 in the City of Galion, between N. East St. and Gelsanliter Rd., is closed for the City’s sanitary sewer project. The detour route for southbound motorists is SR 309/61 (Charles St.) to Gelsanliter Rd., south on Gelsanliter Rd. to SR 97 (Harding Way), west on SR 97 to SR 309/61 (N. East St.) and reverse for northbound motorists. The road is expected to reopen Monday, May 11, 2020. For more information contact the City of Galion Service Department at 419-468-2818.

 

 

ERIE COUNTY
Multiple Overpass Bridge Closure Over State Route 2
The bridges listed below are closed as part of a bridge repair project. Please note the specific closure information for each location listed below:

  • County Road 140 (Joppa Road)
    • At the Joppa Road bridge over SR 2; between Frailey Road and Poorman Road
    • The detour route for northbound motorists is Joppa Road to Darrow Road, west on Darrow Road to Frailey Road, north on Frailey Road to US 6 (Cleveland Sandusky Road), east on US 6 to Joppa Road, and reverse for southbound motorists.
  • Township Road 121 (Camp Road)
    • At the Camp Road bridge over SR 2; between Galloway Road and Rye Beach Road
    • The detour route for northbound motorists is Camp Road to Boos Road, east on Boos Road to Rye Beach Road, north on Rye Beach Road to US 6, west on US 6 to Camp Road, and reverse for southbound motorists.
  • Township Road 135 (Hahn Road)
    • At the Hahn Road bridge over SR 2; between SR 61 and Frailey Road
    • The detour route for northbound motorists is Hahn Road to US 6, west on US 6 to SR 61, south on SR 61 to Darrow Road, east on Darrow Road to Hahn Road, and reverse for southbound motorists.

All of the bridges are expected to reopen on Thursday, May 21, 2020; however, all work is weather dependent and is subject to change.

 

 

HURON COUNTY
State Route 4 ***NEW***
State Route 4, just north on SR 269, will close Monday, May 11 for a culvert replacement. The detour route for the northbound motorists is SR 4 to SR 269, north on SR 269 to SR 547, east on SR 547 to SR 4, and reverse for southbound motorists. The road is scheduled to reopen Friday, May 15, 2020. 

State Route 162
State Route 162, between Miller Road and Section Line Road, is closed for a bridge replacement project. The detour route for westbound motorists is SR 162 to SR 99, south on SR 99 to US 224, west on US 224 to SR 4, north on SR 4 to SR 162, and reverse for eastbound motorists. The project is expected to be complete Monday, May 11, 2020; however, all work is weather dependent and subject to change.

 

 

LORAIN COUNTY
State Route 2 ***NEW***
SR 2 eastbound, just east of the bridge over SR 58 in the City of Amherst, will have a single lane closure for a slide repair project. On Sunday, May 3 at 6:00 p.m., there will be single lane closures to place striping and portable concrete barrier. The lane closures will be in place until Monday, May 4 at 6:00 a.m. Lane widths through this work zone will be narrowed to 10’. The project is expected to be complete September 2020. 

US Route 6: Bridge Repairs ***UPDATE***
US 6, between Washington Avenue and Arizona Avenue, will be reduced to one lane of traffic for bridge repairs on the Charles Berry Bascule Bridge. One lane of traffic for eastbound and westbound vehicular traffic will be maintained no the south side (eastbound lanes) of the bridge. The north side (westbound lanes) of the bridge will be closed to vehicular traffic. Pedestrian traffic will be maintained on either the north or south sidewalk depending on the work and will be clearly marked. The entire project is expected to be complete August 2020. 

US Route 20: Major Widening
US 20, between Stoney Ridge Road and Lear Nagle Road, will have one lane of traffic maintained in each direction. The following are project updates for the upcoming week:

  • The following intersections are closed for the next 30 days as of Monday, April 13 for pavement removal and embankment work: Ridge Plaza Drive, Ridgeview Boulevard, Cornell Avenue, and North Lear Nagle. Paving is tentatively scheduled to begin Wednesday, May 6, from west to east. Signal timing at these intersections are updated to reflect the changes and detours have been posted.
  • SR 83 traffic has been shifted to the west side of SR 83 through Center Ridge Road, heading north and southbound. Pavement removal and embankment construction will continue on the east side of the road. The dedicated left turn lanes have been eliminated and the traffic signal timing will be changed accordingly.
  • Traffic on Emerald Street has been shifted onto the temporary pavement.
  • To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed and watch for stopped traffic while passing by the work zone.
  • Pedestrians and bicyclists should use extreme caution while traveling through the work zone and stay out of the active work area to avoid conflicts with construction vehicles and equipment.

The project is expected to be complete Fall of 2020; however, all work is weather dependent and is subject to change. 

US Route 20: Bridge Replacement
US 20 over Ridgeway Ditch, between Case Rd. and Fowlers Run, will be reduced to one lane of traffic in each direction for a bridge replacement project. The project is expected to be complete May 2020. 

US Route 20: Roadway Improvement
US 20, at the intersections of Cleveland Street/South Abbe Road and Cleveland Street/SR 57, will have single lane closures as needed as crews continue to work on traffic signal replacements at the two intersections in the City of Elyria. Crews continue to complete surface course and final pavement markings. Motorists are advised to use caution when driving in the area. Traffic will be maintained by flaggers during the short-term lane closures for the construction of the traffic signals. The project is expected to be complete May 2020; however, all work is weather dependent and is subject to change. 

County Road 53 (West Ridge Road)
CR 53 West Ridge Road, between Dellfield Road and CR 32 Middle Ridge Road, is closed to northbound traffic ONLY for signalization and resurfacing work. Traffic on Middle Ridge Road will be maintained. The detour route will be south on CR 53 West Ridge Road, west on Telegraph Road/Milan Elyria Road, north on Oberlin Road, east on CR 32 Middle Ridge Road. Southbound traffic on West Ridge Road will be maintained. The project is expected to be complete Wednesday, July 15, 2020.

State Route 254
SR 254 in the Village of Sheffield will have a shoulder closure adjacent to the eastbound right turn lane at the intersection of SR 301. Crews will be completing storm sewer installation, excavation, aggregate base, and preparing for curb installation. The project is expected to be complete June 2020.

State Route 301
SR 301, from SR 254 to College Drive, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers. There will also be single lane closures on SR 301 between SR 611 to Oster Road for concrete pavement repairs. The project is expected to be complete June 2020.

State Route 611
SR 611 in the Village of Sheffield, from Harris Road to Miller Road, will have single lane closures for concrete pavement repairs. Traffic will be maintained by flaggers. The project is expected to be complete June 2020.

 

MEDINA COUNTY
North Carpenter Road
North Carpenter Road, between Grafton Road and Boston Road, is closed for approximately 120 days in order to complete pavement widening, storm sewer work, and other miscellaneous work on the project. During the closure, only northbound traffic will be maintained for local traffic only. All southbound traffic and non-local northbound traffic, between Grafton Road and Boston Road, will be required to use the detour. The detours are as follows:

  • Southbound traffic will be detoured east on Boston Road to West 130th Street, south on West 130th Street to Grafton Road, and west on Grafton Road back to North Carpenter Road.
  • Northbound, non-local traffic will be detoured east on Grafton Road to West 130th Street, north on West 130th Street to Boston Road, and west on Boston Road back to North Carpenter Road.

North Carpenter Road, between Concord Drive and Grafton Road, will continue to have intermittent single lane closures in order to complete miscellaneous work items. Bi-directional traffic will be maintained by flaggers within this section during this time. The entire project is expected to be complete September 2020.

US Route 224 ***UPDATE***
US 224 eastbound and westbound, just past Lake Road before the I-71 ramps, will have single lane closures to complete drainage work in the medians and outside shoulders. US 224 at the Leroy Road intersection is closed for intersection improvements for the installation of left turn lanes. The detour route for motorists headed southbound on Leroy Road will proceed west on US 224 to the U-turn, then east on US 224 to Leroy Road south. The detour route for motorists headed northbound on Leroy road will proceed east on Greenwich Road to Lake Road, north on Lake Road to US 224, west on US 224 to Leroy Road north. This closure is expected to be complete Friday, May 8; however, all work is weather dependent and is subject to change. Traffic in the driving lanes in either direction will be maintained at the normal lane width (12’) at all times. The entire project is expected to be complete August 2020.

State Route 301
SR 301, just south of Crawford Road (TR 80), will close Monday, May 4 for a culvert replacement. The detour route for northbound motorists is SR 301 to US 42, northeast on US 42 to US 224, west on US 224 to SR 301, and reverse for southbound motorists. The road is expected to reopen Friday, May 8, 2020.

 

 

RICHLAND COUNTY
State Route 13
SR 13 in the Village of Bellville, between SR 97 and Ogle Street, will be reduced to one lane of traffic for a bridge repair project. Traffic will be maintained by flaggers. The project is expected to be complete August 2020. 

US Route 30
US 30, from 4th Street to SR 309, will have shoulder closures in both the eastbound and westbound directions for bridge pier work. Crews continue concrete work on bridge piers. The project is expected to be complete August 2020. 

US Route 42
US 42, from Fox Road to the City of Mansfield corporation limit, will have single lane closures for a resurfacing project. Traffic will be maintained by periodic flagging operations as needed. The project is expected to be complete July 2020; however, all work is weather dependent and is subject to change.

US Route 42: Resurfacing
US 42, from the City of Mansfield corporation limits to the Ashland County line, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers. Crews will begin work on catch basins, corrective pavement work, and pavement markings the week of April 27. The project is expected to be complete June 2020. 

Interstate 71
I-71 northbound and southbound, from the Morrow County line to SR 97, will have single lane, day time closures and double lane, night time closures for a resurfacing project. Crews continue night work on I-71 from the Morrow/Richland County line to the SR 13 exit. Work will progress in both zones simultaneously. The project is expected to be complete October 2020.

State Route 603
SR 603, between Pleasant Valley Road and SR 95, is closed for a maintenance repair project on a retaining wall. The detour route for motorists headed northbound on SR 603 will travel east on SR 95 to SR 39, northwest on SR 39 to SR 603, and reverse for southbound motorists. The road is expected to reopen Thursday, May 28, 2020.

 

 

WAYNE COUNTY
US Route 30
US 30, at the intersection of SR 94 in the Village of Dalton, will have single lane closures for intersection improvements. Both US 30 and SR 94 will have lane closures dependent upon the work and traffic will be maintained by temporary traffic control systems when needed. The turn lanes at US 30 and SR 94 will be intermittently closed in order to complete necessary work. The project is expected to be complete May 2020; however, all work is weather dependent and is subject to change.

State Route 83 ***NEW***
SR 83, between Smithville Western Road and North Hutton Road, will close Monday, May 11 for a resurfacing project. The detour route for northbound motorists is SR 83 to SR 3, north on SR 3 to SR 604, west on SR 604 to SR 83, and reverse for southbound motorists. The road is expected to reopen Monday, July 13. 

State Route 94 ***UPDATE***
SR 94, just south of Doylestown Road, is closed for a culvert replacement. The detour route for southbound motorists will be SR 94 to Doylestown Road (CR 70), west on Doylestown Road to SR 57, south on SR 57 to SR 585, north on SR 585 to SR 94, and reverse for northbound motorists. The road is expected to reopen Friday, May 8.

State Route 302 ***NEW***
SR 302, from the intersection of Old Lincoln Way to the Ashland County line, will be reduced to one lane of traffic for a crack sealing project. Traffic will be maintained by flaggers. The project is expected to be complete May 2020.