UPDATE: I-475 widening and Dorr St. interchange project

Having trouble viewing this email? View it as a Web page.

Wordmark

PROJECT UPDATE

Project Update:

I-475 Widening and Dorr Street Interchange

DATE CHANGE Additional local impacts beginning Tuesday, March 24

 

BOWLING GREEN (Tuesday, March 17) - While westbound Dorr St. traffic between Holland-Sylvania Rd. and McCord Rd. remains detoured, work at the McCord Road intersection with Dorr Street requires new traffic impacts.

Beginning Tuesday, March 24, through October:

  • Westbound Dorr St. closure extends 2,000 feet west of McCord Rd.
    Eastbound Dorr St. remains open.
  • Northbound McCord Rd. closed 2,000 feet north and south of Dorr St.
    Southbound McCord Rd. remains open.
Dorr & McCord

 

Crews will use the new lane restrictions to continue utility work along Dorr St., as well as begin removing and replacing wider pavement on the four legs approaching the intersection of Dorr St. and McCord Rd. in preparation for the roundabout that will be constructed later in the project.

Check ODOT's social media for updates: Facebook, Twitter

 

Project information:

The $45.2 million project includes:

  • Widening I-475 from Central Avenue/US 20 to Airport Highway/SR 2
  • Constructing new I-475 bridges over Hill Avenue and Dorr Street
  • Adding a roundabout interchange at Dorr Street
  • Constructing roundabout at Dorr Street and McCord Road

I-475 will remain two, 11' lanes in each direction, with the exception of overnight hours. 

The project being constructed by Miller Brothers Construction is expected to be complete in November 2021.

 


I 475

Interstate 475

Widening and Interchange Construction

Project 470-19/PID 88084

Through Summer 2021

  • Overnight lane restrictions possible on I-475 between Airport Hwy. and Bancroft St.
  • Short term road closures possible on Hill Ave. and Dorr St. between Holland-Sylvania Rd. and McCord Rd. for overhead bridge beam removal
    Traffic maintained by flaggers

Tuesday, March 24 through October

  • Westbound Dorr St. closure extends 2,000 feet west of McCord Rd. 
    Eastbound Dorr St. remains open.
  • Northbound McCord Rd. closed 2,000 feet north and south of Dorr St. Detour: Nebraska Ave.; King Rd.; Bancroft St.
    Southbound McCord Rd. remains open.

Through October

  • Westbound Dorr St. closed between Holland Sylvania Rd. and McCord Rd.
    Detour: northbound Holland Sylvania Rd.; westbound Bancroft St.; southbound McCord Rd.

Additional restrictions will be announced


 

Sign up for construction project information here: https://public.govdelivery.com/accounts/OHDOT/subscriber/new

 

ODOT contact information:

ODOT District 2 public information office
419-373-4428; D02.PIO@dot.ohio.gov


OHGO Logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.


The Ohio Department of Transportation maintains the state's largest man-made asset - the transportation system. ODOT's mission is to provide the safe and easy movement of people and goods from place to place. As a $2.8 billion per year enterprise, ODOT invests the bulk of its resources in system preservation through maintenance, construction and snow and ice operations.

The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.