Williams County September 5 Weekly Construction Update

Having trouble viewing this email? View it as a Web page.

Wordmark
 

Williams County Weekly Construction Update

For Immediate Release

Thursday, September 5, 2019

Updates are highlighted in bold and underlined


US 6

US Route 6

Bridge Replacements

Project 552-18/PID 95997

Through September

US 6 now open between CR 20 and CR 23

Lane restrictions possible for finish work


us 6 route 6

US Route 6

*Work Starts Monday*

Paving and Culvert Repair

Project 407-19/PID 95792

Monday, September 9 through October

Lane restrictions possible on US 6 between US 127 and the Henry Co. Line

 

Tuesday, September 17 through October

Lane restrictions possible westbound between CR 17 and CR 18 for culvert repair


US 20A

US Route 20A/State Route 15

*CLOSURE STARTS FRIDAY*

Ohio Turnpike Project 59-19-01 (R-8)

Friday, September 6 at 12pm (noon) through mid-November

Ramp closed from US 20A/SR 15 to westbound I-80/Ohio Turnpike

For more information contact Ohio Turnpike and Infrastructure Commission


SR 34

State Route 34

Chip Seal

Through mid-September

Lane restrictions possible on SR 34 between Blakeslee and Bryan


SR 49

State Route 49

Pavement Repairs

Through Friday, August 30

SR 49 now open between CR-N 30 and US 20

*Project Complete*


SR 107

State Route 107

Resurfacing and Bridge Rehabilitation

Project 31-19/PID 101346

Through September

Lane restrictions on SR 107 between Montpelier and SR 15

Pedestrian access maintained over bridge between N. Airport Rd./CR 13 and CR 12.5


Various Routes District-wide

Guardrail & Electrical Maintenance

Projects 1052-17, 1050-18 & 1059-17/PIDs 103414, 103373, 106115

Through December

Lane restrictions are possible district-wide


**All work is weather permitting.**

For more information contact: 

The District Two Public Information Office at

(419) 373-4428
or email D02.PIO@dot.ohio.gov


OHGO.com logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.


The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.