Wood County Weekly Construction Update
For Immediate Release
Thursday, May 9, 2019
Updates are highlighted in bold and underlined
 |
|
Interstate 75
State Route 64/Wooster St. Interchange
Project 408-18/PID 101007
Through August
Lane restrictions possible on I-75 between Poe Rd. and Napoleon Rd.
Sidewalk restrictions possible on SR 64/Wooster St.
Pedestrian access maintained
Through Sunday, May 19
- Westbound Wooster St. over I-75 will be closed
Detour: Dunbridge Rd.; Poe Rd.; Mercer Rd.
- Eastbound Wooster St. over I-75 will be maintained
Through July
- The ramp from Wooster St. to northbound I-75 will be closed
Detour: Dunbridge Rd.; US 6; I-75
Monday, May 20 through July
- Wooster St. over I-75 will be closed (ramps open except Wooster St. to northbound I-75 ramp)
Detour: Dunbridge Rd.; Poe Rd.; Mercer Rd.
Future restrictions and closures will be announced
|
 |
|
Interstate 75
*NEW WORK*
Pavement Repair
Project 237-14/PID 25521
Friday, May 10
Lane restrictions possible on northbound I-75 between Roachton Rd. and I-475
|
 |
|
Interstate 280
Five Bridge Paintings
Project 618-18/PID 101350
Through September
Lane restrictions possible under the following bridges: Bahnsen Rd.; SR 795; Wales Rd.; SR 51; Curtice Rd.
Through Monday, May 22
- Ramp from southbound I-280 to Curtice Rd. and Woodville Rd. (Exits 6A and 6B) closed for bridge painting Detour: Walbridge Rd. (Exit 4)
- Ramp from Woodville Rd. and Curtice Rd. to southbound I-280 closed
Detour: northbound I-280; Wheeling St. (Exit 7); southbound I-280
Ramp closures may be announced
|
 |
|
Interstate 280/SR 420
Widening and Replacement of Ohio Turnpike Bridge Deck over I-280/SR 420
Ohio Turnpike project 43-19-03
Through September
- The ramp from southbound I-280 to Ohio Turnpike (Exit 1A) will be closed
Detour: J-turn south of Libbey Rd.; northbound SR 420; I-80/90 (Exit 1A)
- The ramp from Ohio Turnpike to southbound SR 420 will be closed
Detour: northbound I-280; Bahnsen Rd. (Exit 1B); southbound I-280
For more information contact Ohio Turnpike and Infrastructure Commission
|
 |
|
US Route 20
Pavement Widening & Turn Lane Installation
Project 434-18/ PID 103744
Through Saturday, May 18, daily 7:30am to 5:30pm
Lane restrictions possible at US 20 and SR 163 for slope and ditch repair
|
 |
|
State Route 64
Waterville Bridge Replacement
Project 567-17/PID 92088
Through September 2020
Lane restrictions possible
One weekend closure in 2019 (dates TBA)
Memorial Park remains closed through October 2020
|
 |
|
State Route 281 *WORK BEGINS WEDNESDAY*
Resurfacing and Bridge Work
Project 530-18/PID 102824
Wednesday, May 15 through Friday, May 17
SR 281 closed between Hoffman Rd. and Cloverdale Rd. for bridge work
Detour: SR 25; US 6; SR 199
|
 |
|
State Route 420
Pavement Repair
*WORK COMPLETE*
|
 |
|
State Route 420
*WORK BEGINS MONDAY*
Resurfacing
Project 146-19/PID 107059
Monday, May 13 through Friday, May 17
Lane restrictions possible on SR 420 between SR 163 and Libbey Rd.
|
 |
|
State Route 582 *CLOSURE BEGINS MONDAY*
Minor Widening and Bridge Rehabilitation
Project 166-19/PID 81000
Monday, April 22 through October
Lane restrictions between I-75 and SR 199
Through Friday, May 10
- SR 582 between I-75 and SR 199 closed for crossover installation
Detour: SR 199; Roachton Rd.; SR 25
Monday, May 13 through October
- SR 582 between I-75 and SR 199 closed to through traffic
- Detour: SR 199; Roachton Rd.; SR 25
- Residential access maintained
Monday, May 13 through mid-June
- SR 582 bridge over I-75 will be closed for rehabilitation
- SR 582 will be closed between Carter Rd. and Caris Rd. for culvert installation, drainage work, and roadway reconstruction
- North-south roads including SR 199 will remain open
- Detour: SR 199; Roachton Rd.; SR 25
Wednesday, May 29 through mid-June
- Ramps to/from I-75 to/from SR 582 will be closed Detours: US 6 (Exit 179); SR 199 or I-475 (Exit 192); SR 25 (Exit 2)
Additional restrictions and closures will be announced
|
Buck Road
*UPDATE*
Roundabout Construction at Lime City Rd. and Penta Career Center
Projects 373-18/PID 83312
Through May
Lane restrictions possible for drainage work
Wednesday, May 22 through mid-September
Lane restrictions at Lime City Rd. and Buck Rd. for roundabout construction
Wednesday, May 22 through July
-
Buck Rd. eastbound traffic only between Bates Rd. and Lime City Rd.
Detour: Lime City Rd.; Schreier Rd.; River Rd./SR 65; Bates Rd.
-
Lime City Rd. southbound traffic only between Buck Rd. and Mandell Rd.
Detour: Mandell Rd.; Bates Rd.; Buck Rd.
Various Routes District-wide
Guardrail & Electrical Maintenance
Projects 1052-17, 1050-18 & 1059-17/PIDs 103414, 103373, 106115
Through December
Lane restrictions possible district-wide
**All work is weather permitting.**
For more information contact:
The District Two Public Information Office at
(419) 373-4428 or email D02.PIO@dot.ohio.gov
Know Before You Go!
For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.
|
The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.
|