Upcoming ODOT Work This Week
Through the week ending September 29, 2018: The following traffic advisory includes road construction
and major maintenance projects requiring long-term lane restrictions and/or
closures along the state and federal highway system in Jackson County.
For statewide information regarding road conditions affected by weather,
construction, maintenance or accidents, visit ODOT on the web at www.Ohgo.com
JACKSON COUNTY:
MONDAY, SEPTEMBER 24:
S.R. 279 will be closed between T.R. 26 (Snyder Road) and C.R. 8 (Tommy Been
Road) at Jackson Lake for a culvert replacement project. The project site is
situated at the junction with Snyder Road and T.R. 904 (Lakeview Drive), and
while the route is closed, motorists will be detoured via S.R. 93, S.R. 32 and
S.R. 139. All work is scheduled to be completed in mid-fall. (#18-0258)
A resurfacing
project is under way on S.R. 327 in the city of Wellston, where crews
will be paving the route from just south of C.R. 78 (Fairgreens Road) to the
north corporation limit. Throughout construction, traffic will be maintained in
one lane with the use of flaggers and/or temporary signals, and all work is
scheduled to be completed in early fall. (#18-0227)
A
resurfacing project is under way on U.S. 35, where crews will be
paving the route from just west of the
S.R. 93 interchange to the S.R. 327 intersection. Throughout construction, traffic will be maintained in a
minimum of one lane in each direction, and the project is scheduled to be
completed in late fall. (#18-0289)
S.R.
776 is closed between T.R. 244 (Mayhew Road) and T.R. 1046 (Mineral
Heights Road) for a bridge replacement project. The closure will be in effect
for up to 45 and days, and while the route is closed, motorists will be
detoured via S.R. 32 and S.R. 139. The project is anticipated to be completed
in early fall. (#18-0201)
Intermittent lane restrictions will be in effect on S.R.
327, between T.R. 513 (Thornton Road) and T.R. 153 (June Marshall Road), for
paving operations following a bridge replacement project. Throughout
construction, traffic will be maintained by flaggers when crews are at work. The
entire project is scheduled to be completed in late summer. (#18-0201)
A preventive maintenance project
on S.R. 93 has been suspended temporarily. Crews will return in early fall to
complete striping and finishing work on the route, between T.R. 738 (Cedar
Street) at the southern corporation limit of Oak Hill and T.R. 601 (Sternberger
Road). Currently, there is no impact to traffic; however, when crews return to
the site, traffic will be maintained by flaggers. (#18-0022)
For more information contact: Kathleen Fuller, public information officer ODOT District 9 (o) 740-774-8834; (m) 740-637-9037
 Know Before You Go!
For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.
|
The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.
|