ODOT District 3 Weekly Construction
Report
For
the Week of August 13
ASHLAND COUNTY
 |
|
US
Route 42 ***NEW***
US 42, at the intersection of King Rd., will have traffic
maintained with flaggers as needed, as crews begin underground work on signals.
The project is expected to be complete August 2018. |
 Interstate 71 ***UPDATE*** I-71, from US 250 to the Wayne County line, will
have intermittent single lane closures during the day and double lane closures
at night for a resurfacing project. Crews
will be paving the southbound lanes
and both the north and southbound entrance and exit ramps at US 250. Traffic
will be maintained on the ramps with narrowed lanes. Nightly resurfacing
repairs will take place from 8pm-7am. Motorists are advised to drive with
caution through the area as trucks enter and exit the work zone. The project will utilize
digital speed limit signs to maintain traffic flow. The posted speed limit when
crews are NOT working will be 65 mph; the reduced speed limit when workers are
present will be 55mph. The project is expected to be
complete August 2018.
|
 |
|
State
Route 89
SR 89,
just south of CR 2000, is now closed for a culvert replacement. The detour
route for southbound motorists is SR 89 to US 30, west on US 30 to SR 60, south
on SR 60 to SR 179, southeast on SR 179 to SR 95, northeast on SR 95 to SR 89,
and reverse for northbound motorists. The road is expected to reopen Wednesday,
August 15, 2018.
|
 State Route 95
SR 95, from just east of Green TR 2704 moving east consecutively to just west
of Ashland CR 37, is closed for multiple culvert replacements. Crews will consecutively move west to east
along SR 95 to complete all seven culverts; four of the seven culverts have
been completed. The location and time frame for each culvert is as follows: A.)
August 6-August 10: between TR 2402 and TR 457, B.) August 13-August 17: just
west of SR 89, C.) August 20-August 24: just west of CR 37. The detour
route is the same for all seven culverts. Motorists heading northeast should
travel SR 95 to SR 39, southeast on SR 39 to SR 3, northeast on SR 3 to SR 95,
and reverse for southwest motorists. The road is expected to reopen Friday,
August 24, 2018.
|
 |
|
US
Route 250 ***NEW***
US 250, at its intersection with Sugarbush Dr. and George Rd., will have traffic
maintained with flaggers as needed, as crews begin underground work on signals.
The project is expected to be complete August 2018.
|
County Road 1302
CR 1302, at the
structure over I-71, is closed for bridge repairs. The detour route for
westbound motorists is CR 1302 to SR 89, north on SR 89 to US 42, southwest on
US 42 to CR 1302, and reverse for eastbound motorists. The road is expected to
reopen Sunday, August 19, 2018.
 Know Before You Go!