For the Week of May 28

There will be no new work impacting traffic through the Memorial Day weekend.
ODOT works with its contractors to reduce the size of work zones and open as many lanes as possible. All work will resume Tuesday, May 29.

 

ASHLAND COUNTY

SR 39

State Route 39
SR 39, east of Wally Rd. over Black Fork of the Mohican River, will have signalized, single lane closures to maintain traffic for a bridge replacement. Crews are working on the eastbound side of the bridge. All traffic has been shifted to the westbound lane. The project is expected to be complete June 2018.

US 30

US Route 30
US 30, from SR 511 to SR 60, will have single lane closures as crews continue pavement repairs. The project will utilize speed limit signs to reduce the speed and maintain the flow of traffic. The reduced speed limit when workers are present will be 50 mph; the posted speed limit when crews are NOT working will be 60 mph. The project is expected to be complete July 2018.

I 71

Interstate 71
I-71, from US 250 to the Wayne County line, will have intermittent single lane closures as crews begin work as part of a resurfacing project. Crews will begin paving southbound in the farthest pasting lane. This work will be performed during night time hours. Nightly pavement repairs will take place from 8pm-7am. Double lane closures at night have gone into effect leaving one lane of traffic open in both directions. The project will utilize digital speed limit signs to maintain traffic flow. The posted speed limit when crews are NOT working will be 65 mph; the reduced speed limit when workers are present will be 55mph. The project is expected to be complete May 2018.

Township Road 653
TR 653, between US 250 and TR 685, will close Wednesday, May 30 for bridge repairs. The detour route for northbound motorists is to take US 250 east to TR 593, north on TR 593 to TR 1302, west to TR 1302 back to TR 653, and reverse for southbound motorists. The project is expected to be complete September 2018.

 

Goon Rd. (CR 3006)
Goon Rd., along with other roadways within Mohican State Park, will have intermittent lane closures as part of a resurfacing project. Traffic will be maintained by flaggers. Notices of roadwork are marked along State Park roads. The project is expected to be complete August 2018.


OHGO.com logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.


The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.