ODOT Ross County: Travel Report

Having trouble viewing this email? View it as a Web page.

Wordmark

Construction Update 

Upcoming ODOT Work This Week

For the week ending May 19, 2018: The following traffic advisory includes road construction and major maintenance projects requiring long-term lane restrictions and/or closures along the state and federal highway system in Ross County. For statewide information regarding road conditions affected by weather, construction, maintenance or accidents, visit ODOT on the web at www.Ohgo.com

ROSS COUNTY

MONDAY, MAY 14: Construction for a slide repair is scheduled to begin on U.S. 35 in the eastbound direction near the C.R. 213B (Musgrove Road) overpass, three miles west of the C.R. 207 (Watson Road) interchange at Richmond Dale. Throughout construction, traffic will be maintained in one, 12 lane in either direction, and the project is scheduled to be completed in early fall. (#18-0178)

Operations for a resurfacing project on C.R. 550 have resumed, and crews will be completing milling and paving work between the U.S. 35 interchange at Pleasant Valley and S.R. 138, and traffic will be maintained in one lane by flaggers during hours of operation. All work is scheduled to be completed in early summer. (#17-0488)

Construction has begun for the Industrial Drive extension off Gateway Drive in Chillicothe. The project is to extend the existing industrial park roadway south toward the access road off S.R. 104. As work will be conducted off the existing roadways, there should be little to no impact to traffic. The project is scheduled to be completed in mid-summer. (#17-0558)

As part of a districtwide bridge maintenance project, restrictions will be in effect on S.R. 138 between the intersections with Austin Road, just west of U.S. 35, for crews to repair expansion joints. Traffic will be maintained in one lane by flaggers, temporary signals and/or arrow boards when crews are at work. (#18-0157)

Lane restrictions are in effect on S.R. 772, between C.R. 184 (Rozelle Creek Road) and T.R. 906 (Streevey Lane) for a culvert replacement project. Traffic is being maintained in one, 9-foot lane with temporary signals, and the anticipated completion for all work is mid-summer. (#17-0372)

Preliminary operations for a bridge scour/bank stabilization project at the Paint Creek Bridge on U.S. 23, just south of Chillicothe, have been completed. Crews will return to the site in mid-June to complete the project, but as most work will be conducted off the roadway, there should be little to no impact to traffic. The entire project is scheduled to be completed in mid-summer. (#18-0032)

Operations have resumed for a slide repair project on U.S. 50, between T.R. 38 (Dill Road) and T.R. 150 (California Hollow Road), where crews have finishing work to complete along the shoulder of the route. As most work will be completed off the roadway, there should be little impact to motorists; however, traffic will be maintained in one lane by flaggers as needed. All work is scheduled to be completed in late spring. (#16-0516)

For more information contact:
Kathleen Fuller, public information officer
Ohio Department of Transportation - District 9
(o) 740-774-8834; (m) 740-637-9037


OHGO.com logo

Know Before You Go!

For more detailed traffic information, and to get personalized traffic alerts for your commute, download the OHGO app or visit OHGO.com.


The environmental review, consultation and other actions required by applicable Federal environmental laws for these projects are being, or have been, carried out by ODOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 11, 2015, and executed by FHWA and ODOT.