 Please note that construction schedules are subject to change due to weather, site issues, etc.
Reference this MAP to view the impacted construction areas and expected lane/road changes for next week.
North Linden - 1 Construction Update Week of November 11, 2024
Important Notice: Temporary lane/road shifts or closures are noted on the map.
OAKLAND PARK-MEDINA
Area 1: 3042-3048 Bremen St. -- Sanitary Lateral Lining
Area 2: 1457-1485 Weldon Ave. -- Sanitary Lateral Lining
Area 3: 2956-2971 Medina Ave. -- Sanitary Lateral Lining
HUDSON-MCGUFFEY
Area 4: 1265-1330 E. Weber Rd. -- Permeable Pavers Installation
Area 5: 2742-2790 Ontario St. -- Green Infrastructure Installation
Area 6: 2600-2645 Ontario St. -- Green Infrastructure Installation
Area 7: 1492-1570 E. Weber Rd. -- Permeable Pavers Installation
Area 8: 2325-2762 Dresden St. -- Green Infrastructure Installation
Area 9: 1435-1457 Genessee Ave. -- Sanitary Lateral Lining
Area 10: 1426-1452 Arlington Ave. -- Sanitary Lateral Lining
Area 11: 1529-1541 Arlington Ave. -- Sanitary Lateral Lining
Area 12: 1526-1536 Myrtle Ave. -- Sanitary Lateral Lining
AGLER-BERRELL
Area 13: Genessee Ave. -- Downspout Installations
Area 14: Joyce Ave. -- Downspout Installations
ARTANE-PARKWOOD
No Scheduled Work
REMINDER -- View the map for details about road/lane changes for next week.
Unsure about which is your area? Visit the Blueprint map and enter your address to find out!
Sump pump installations are offered for a limited time only! Contact us and we’ll get you on the waitlist for your no-obligation assessment!
Reminder: If you have a basement backup (sewer water coming up from your floor drain), please report this to the City by calling 614-645-7102. Please note that crews are working diligently to investigate issues throughout the city, so response will not be immediate. We appreciate your patience and understanding.
|