The NMED, Air Quality Bureau has updated both NSR and Title V fees to incorporate the Consumer Price Index (CPI) adjustments as required by 20.2.75 and 20.2.71 NMAC, respectively.  

NSR Construction Permit Fees:  

  1. The new NSR fee point is $408.  
  2. The GCP & Streamline permit fee for new facilities is $4,080.
  3. The new Relocation Fee is $408.
  4. The new NSR annual fee is now $1943.

Title V Fees: 

  1. The new Title V annual fee is $30.77 per ton.
  2. The corresponding Title V HAP fee is $195.53 per ton.

Changed documents:  The following documents have been updated to reflect these changes:

  1. All the GCP application forms (Multi-Forms)
  2. The Universal Application Form 
  3. The Construction Permit Fee Calculator

 

How much should I submit with my application?  For applications requiring a $500 filing fee, continue to submit $500 with the application.  You will be invoiced the correct balance due for the permit fee.  For applications that require the full permit fee to be paid with the application, submit the following:

  1. $4,080 should be submitted with all GCP and Streamline applications.
  2. $408 should be submitted with all Relocation applications

More information about these fees and the CPI methodology used to adjust them on an annual basis can be found at:

https://www.env.nm.gov/air-quality/permit-fees-2/ 

If you have questions or comments concerning this fee process, please contact Donna Intermont at her e-mail address below.  

Donna Intermont

Operations Manager, Air Quality Bureau

 



For additional information concerning this bulletin, please contact Donna Intermont at:  donna.intermont1@state.nm.us