October Project Highlights
Here's what you should know about City of Raleigh street and sidewalk projects.
 Buck Jones Road Widening:
Carolina Sunrock, the City’s contractor, has completed the project. The landscape contractor will plant some more trees this fall and continue to water trees and shrubs planted along the corridor for one year.
 Mitchell Mill Road
New curb and gutter and pavement continues to be installed at the Forestville Mitchell Mill Road intersection. Crews have also started the installation of new traffic signals.
Pullen Road Extension Project:
The Pullen Road extension is taking shape. Carolina Sunrock, the City’s contractor, completed most of the base pavement along the corridor. The landscaping is scheduled for installation this fall.
Roadway Design and Construction Project Update Report
The monthly report on the Roadway Design and Construction Division’s street and sidewalk projects throughout the City of Raleigh:
|