18th Avenue NE Reconstruction- Paving bituminous trail

Topic bulletin header
Having trouble viewing this email? View it as a Web page.

 

Friday August 24, 2018

 

Good Afternoon

1

2

Park Construction installed the first of two layers of asphalt on the shared used trail Wednesday. They were scheduled to install the final 2" lift this morning but had to postpone due to heavy rain. They will pave the final layer tomorrow, Saturday 8/25.

Once the trail is completed, the concrete contractor can complete the remaining pedestrian ramps, driveways and sidewalks. This will include the intersection of Central to allow the signals to be installed. The concrete crew are scheduled to return mid week next week.

Park will also start grading the edges of the sidewalks and boulevards for new topsoil and sod next week. Work on the street can then be completed, raising the manholes and paving the final layer of asphalt.. Further notice will be given prior to street paving.

 

Please be aware schedules are subject to change due to weather conditions.

 

If you have any questions or concerns, please call myself John Benjamin 651 443 1096, or Beverly Warmka (Project Manager) on 612 673 3762.

 

Thank you!