 Chankahda Trail Project Update - Oct. 8, 2026
Stage 3B
Chankahda Trail is closed from Cheshire Parkway to Yucca Lane. The south leg of the Yucca Lane intersection is closed. Chankahda Trail and the south leg of Yucca Lane will reopen in November 2026. (See Detour and Staging Map below)
Below is a summary of construction activities completed this week and planned for next week.
Week of October 5
- Storm sewer installation continues between Cheshire Parkway and Annapolis Lane.
- Construction of the retaining wall between Dallas Lane and Annapolis Lane.
Week of October 12
- Grading for the road and trails between Cheshire Parkway and Annapolis Lane.
- Installing the gravel base in preparation for curb and gutter between Cheshire Parkway and Yucca Lane.
The Stage 3B detour and staging map is available below.
See Detour and Staging Map (PDF)
If you have questions or concerns during the construction of this project, please contact Joe Shamla, Assistant City Engineer (City of Plymouth) at 763-509-5541 or jshamla@plymouthmn.gov
|
|
|
|