 Chankahda Trail Project - Construction Update
Stage 3A
Chankahda Trail remains closed between Yucca Lane and Northwest Boulevard. The segment of Chankahda Trail between the Sycamore Lane roundabout and Northwest Boulevard is anticipated to reopen in mid-August.
Below is a summary of construction activities completed this week and work planned for next week.
Week of July 27
- Complete watermain installation in Stage 3A.
- Construct the stormwater basin at the corner of Northwest Boulevard.
- Continue preparing the road base between Yucca Lane and Sycamore Lane.
- Install pedestrian curb ramps between Sycamore Lane and Northwest Boulevard.
- Install pedestrian push buttons at the Northwest Boulevard intersection.
Week of August 3
- Continue road base construction between Yucca Lane and Sycamore Lane.
- Complete the storm sewer and stormwater basin in Stage 3A.
- Begin construction of the retaining wall near Highway 494.
- Construct the trail between Sycamore Lane and Northwest Boulevard.
A detour and staging map is available by clicking the link below.
See Detour and Staging Map
If you have questions or concerns during the construction of this project, please contact Joe Shamla, Assistant City Engineer (City of Plymouth) at 763-509-5541 or jshamla@plymouthmn.gov
|
|
|
|