General Updates
- Please note that schedules are weather-dependent. Updates will be provided approximately once a week moving forward.
- See Project Phasing Map. (PDF)
-
Amhurst Area
- Week of June 8
- City’s Contractor cleanup and demobilization
- Week of June 15
- City’s Contractor cleanup and demobilization
- Week of June 22
- City Forces will begin preparing the roads for milling during the week of June 29. Paving is planned for after the July 4 holiday.
-
Zachary Lane
- Week of June 8
- Road closure to begin June 3 on Zachary Lane (See Detour Map)
- Finish any tree removal remaining
- Complete any remaining tree removals
- Continue curb removals
- Begin curb replacement and asphalt patching
- Continue utility spot replacements
- Continue trail construction
- Week of June 15
- Complete final grading and paving of the trail
- Begin vegetation restoration
- Continue asphalt patching adjacent to curbs
-
Holly Lane
- Weeks of June 8
- Complete any remaining tree removals
- Week of June 15
- No work is planned. The contractor intends to complete work on Zachary Lane before beginning utility, curb, and pavement work on Holly Lane.
For any questions, contact Matt Tang at 763-509-5529 or email mtang@plymouthmn.gov
|
|
|
|