General Updates
- Please note that schedules are weather-dependent. Updates will be provided approximately once a week moving forward.
- See Project Phasing Map.
- The City’s contractor will begin with Phase 1 (Amhurst Area)
-
Amhurst Area
- Week of May 25 (no work on Memorial Day)
- Restart additional utility spot replacements
- Restart curb replacement and asphalt patching
- Continue vegetation restoration
- Week of June 1
- Continue vegetation restoration
- Continue curb replacement and asphalt patching
- Week of June 8
- City’s Contractor cleanup/demobilize
-
Zachary Lane
- Week of May 25 (no work on Memorial Day)
- Private utilities will continue to relocate in preparation for the City’s Contractor to start later this summer.
- Road closure advance warning signs to be installed
- Week of June 1
- Road closure to begin June 3 on Zachary Lane
- Start curb removals
- Remove existing bike trail pavement
- Start utility spot replacements
- Start tree removal
- Week of June 8
- Start curb replacement and asphalt patching
-
Holly Lane
- Week of May 25 (no work on Memorial Day)
- Private utilities will continue to relocate in preparation for the City’s Contractor to start later this summer.
- Week of June 1
- Week of June 8
- No work planned. Contractor plans to finish Zachary Lane before doing utilities, curbs, and pavement on Holly Lane.