 Phase 3 Chankahda Trail Project Update
Stage 1A – Vicksburg Lane to Niagara Lane
Phase 3 construction is underway, and Chankahda Trail between Vicksburg Lane and Niagara Lane is closed. The roadway is expected to reopen later this summer. View the detour and staging map.
Below is a summary of construction activities for this week and a preview of planned work for next week. Please note schedules are subject to weather conditions. Email updates will continue to keep you informed.
This Week : Week of July 14
Looking Ahead : Week of July 21
- Roadway and trail base construction will continue.
- The first layer of pavement will be placed on the new roadway.
Please continue to drive slowly and cautiously in the neighborhoods surrounding Chankahda Trail and allow extra time for travel. We appreciate your patience!
Project Contacts
If you have questions or concerns during the construction of this project, please contact one of the representatives below.
Phil Vigen, Construction Project Representative (Kimley Horn) 612-597-1736 or Phil.Vigen@kimley-horn.com
Jared Buchanan, Project Manager (Kimley Horn) 651-456-8151 or jared.buchanan@kimley-horn.com
Joe Shamla, Assistant City Engineer (City of Plymouth) 763-509-5541 or jshamla@plymouthmn.gov
|