Below is a summary of construction activities for this week and a preview of planned work for next week. Please note schedules are weather-dependent. Updates will be provided approximately once a week moving forward.
This Week – Week of June 2
13th Avenue and Kimberly Lane
- Installation of the gravel road section and new curb (see note in 'Additional Information' section below)
10th Avenue
- Installation of watermain and water services
Looking Ahead – Week of June 9
13th Avenue and Kimberly Lane
- Reconstruction of the road gravel section
11th Avenue
10th Avenue
- Installation of the storm sewer
Additional Information
Note about Newly Poured Concrete
Newly poured concrete curb and gutter should not be driven on for 7 days. Residents in the 13th Avenue and Kimberly Lane areas are allowed to park on the street if needed during this time.
Reminder About Driveway Access
Property owners within the construction area will continue to have access to their driveways before 7 a.m. and at the end of each workday. However, there will be times when driveway access is temporarily restricted. When this occurs, affected homeowners will be notified in advance.
We encourage residents to plan ahead and limit trips to and from their properties during construction. Thank you for your continued patience as we work to complete this project safely and efficiently.
For construction-related questions, residents can contact Dave Buganski, Plymouth’s construction representative, at dbuganski@plymouthmn.gov or 763-509-5530.
|