 Frick's Garden Reconstruction Project
Below is a summary of construction activities for this week and a preview of planned work for next week. Please note schedules are weather-dependent. Updates will be provided approximately once a week moving forward.
This Week – Week of May 12
13th Avenue and Kimberly Lane
- Installation of the storm and sanitary sewers continues
10th Avenue
- Removal of the existing asphalt and set up of the temporary water system continues
Looking Ahead – Week of May 19
13th Avenue and Kimberly Lane
- Reconstruction of the road gravel section begins
10th Avenue
- Residential connection to the temporary water system and installation of the watermain begins
-
Water shutdown expected: Residents on 10th Avenue can expect a 10-30 minute water service interruption while the temporary water system is connected to each home. A construction representative may need to enter homes to verify the connection is functioning correctly. Homeowners will be notified in advance of any connection work.
Reminder About Driveway Access
Property owners within the construction area will continue to have access to their driveways before 7 a.m. and at the end of each workday. However, there will be times when driveway access is temporarily restricted. When this occurs, affected homeowners will be notified in advance.
We encourage residents to plan ahead and limit trips to and from their properties during construction. Thank you for your continued patience as we work to complete this project safely and efficiently.
For construction-related questions, residents can contact Dave Buganski, Plymouth’s construction representative, at dbuganski@plymouthmn.gov or 763-509-5530.
|
|
|
|