 2025 Street Rehabilitation Project Update
Below is a summary of construction activities for this week and a preview of planned work for next week. Please note that schedules may shift due to weather. Weekly updates will continue to keep you informed.
This Week - Week of May 5
Mission Area:
- Saw cutting of curb and gutter and preparation for curb removal
- Private utility relocations
Seven Greens/Silverthorne Area:
- Private utility relocations
6th Avenue:
- Installation of temporary mailboxes for residents
- Private utility relocations
Next Week - Week of May 12
Mission Area:
- Spot curb and gutter removal and replacement
- Removal and replacement of utilities including water valves, hydrants and manholes
- Continued private utility relocations
Seven Greens/Silverthorne Area:
- Continued private utility relocations
6th Avenue:
- Curb and gutter removal
- Removal and replacement of utilities including water valves, hydrants and manholes
- Continued private utility relocations
Water Outage Notice – Mission and 6th Avenue Areas
Some properties in the Mission and 6th Avenue areas will experience a 6-8 hour water outage during utility replacement work. Affected residents will receive a paper notice with additional details and anticipated outage times for each property.
For construction-related questions, residents can contact Matt Tang, Plymouth’s construction representative, at MTang@plymouthmn.gov or 763-509-5529.
|
|
|
|