Birchwood Estates Reconstruction Project Update
Please note, all dates are weather dependent and subject to change.
Phases A1 and A2 The contractor is nearly complete with this phase for most properties. The contractor will continue to complete restoration and punch list items in this phase.
Phase B The contractor is nearly complete with this phase for most properties. The contractor will continue to complete restoration and punch list items in this phase.
Phase C The contractor is nearly complete with this phase for most properties. The contractor will continue to complete restoration and punch list items in this phase.
Phase D The contractor is completing the gravel preparation and plans to pave the first layer of asphalt on Oct 19. Please avoid parking on the road during this phase. Black dirt and final grading is planned for the week of Oct 21.
Sod Replacement Guidelines and Maintenance Sod installed with the project will be maintained by the contractor for the first 30 days only. City staff will inspect the sod at the end of the 30-day period and have the contractor replace any areas in poor condition. After this initial 30 days, maintenance and care of the sod will be the responsibility of the property owner. Neither the contractor nor the city will be responsible for replacing dead sod once it is the property owner’s responsibility to maintain. Below are some guidelines to help care for new sod:
- While the contractor is responsible for sod maintenance for the first 30 days, property owners are encouraged to provide additional assistance if needed to help ensure the long-term success of the sod. This includes watering if you notice the sod is drying out in between days of the contractor’s watering.
- It is important for residents to not mow during the first 30 days.
- Avoid walking on the new sod for the first couple of weeks after installation as much as possible.
- Be patient, areas of damaged sod will often recover.
- It may take a few growing seasons before the sod is fully established to the hearty condition of the rest of the yard.
The city’s construction inspector, Drew Bailey, will be onsite regularly during construction and is available to answer questions. His contact information is drew.bailey@bolton-menk.com or 763-358-1045.
|