Sept. 27 Construction Update
The utility crew will finish most of the utilities along the corridor early next week. Concrete crews will begin paving the northbound lanes of the 35th Avenue intersection and will install sidewalk between 36th and 37th Avenue.
Week of Sept. 30 The grading crew will prepare the road base on 34th Avenue (post office). The street light bases will be installed between 36th Avenue and Rockford Road. The concrete in the northbound lanes at 35th Avenue will be poured. Concrete will be finished between the north side of the 36th Avenue intersection and Rockford Road. Disturbed areas between 36th and 37th Avenue will be restored with topsoil and seed.
All work referenced above is weather dependent.
The project is currently in Phase 1 of construction. Information on how to access key destinations and detour maps are available in the "Phase 1" accordion on the project webpage.
|
|
|
|