Sept. 20 Construction Update
Storm sewer and watermain will be installed at the 34th Avenue intersection (post office). Grading of the road and installation of curb and gutter will occur from 36th Avenue to 37th Avenue. The first layers of bituminous road will be installed between 36th Avenue and Rockford Road in the southbound lanes.
Week of Sept. 23 The contractor will be grading between 36th and 37th Avenue. The concrete steps will be poured at 35th Avenue near the Hilde entrance. The initial layers of pavement (bituminous) will be installed between 36th and 37th Avenue in the northbound direction. Watermain, storm sewer, and sanitary sewer will be constructed at the 34th Avenue intersection (post office).
All work referenced above is weather dependent.
The project is currently in Phase 1 of construction. Information on how to access key destinations and detour maps are available in the "Phase 1" accordion on the project webpage.
|
|
|
|