Sept. 13 Construction Update
Curb and gutter are being constructed in the southbound lanes of Plymouth Blvd. from Rockford Road to 37th Avenue. It will also be installed in the 37th Avenue roundabout, and between 36th and 37th Avenues. The contractor is constructing sanitary sewer and watermain near the 34th Avenue (post office) intersection.
Week of Sept. 23 Grading will take place along the corridor to prepare for sidewalks and trails. The base course of pavement will be installed from Rockford Road to 34th Avenue (city hall).
All work referenced above is weather dependent.
The project is currently in Phase 1 of construction. Information on how to access key destinations and detour maps are available in the "Phase 1" accordion on the project webpage.
|
|
|
|