Sept. 5: 2024 Street Rehabilitation Project Update
All timelines are approximate and weather dependent
General Notes for All Project Areas The city’s construction inspector, Moe Omer, will be onsite regularly during construction and is available to answer questions. His contact information is momer@plymouthmn.gov or 763-509-5529.
Mapledell Paving should be completed early next week with sweeping/clean up to follow. Irrigation repairs are completed in this neighborhood. Please test your irrigation systems and call Moe if you are still having issues. The contractor will be finishing punch list and warranty items over the next few weeks, including irrigation repairs.
Heritage/Medicine Lake Highlands The contractor has completed paving this neighborhood (excluding Rosewood Lane). Irrigation repairs are completed in this neighborhood. Please test your irrigation systems and call Moe if you are still having issues. The contractor will be finishing punch list and warranty items over the next few weeks, including irrigation repairs.
Rosewood Lane, south of 34th Avenue, was base paved on August 22. The contractor will let this road settle for a few weeks. Patches of settled asphalt will be replaced prior to the final layer of pavement installation. The contractor plans to raise the manholes and gate valves next week.
Westridge Estates/Forster Preserve Milling of the neighborhood roads is anticipated to begin the week of September 9. Irrigation repairs are completed in this neighborhood. Please test your irrigation systems and call Moe if you are still having issues.
Nathan Lane, Schmidt Lake Road, 45th Avenue, Highway 169 Service Drive The contractor is planning to pave the trail the week of September 9.
|