Aug. 30: 2024 Street Rehabilitation Project Update
All timelines are approximate and weather dependent.
General Notes for All Project Areas
Please turn off irrigation zones near the street while the contractor is working on curb removal/replacement.
Newly poured curb takes 7 days to harden and should not be driven on during this time. Owners should park on the street and have cars out of the construction area during the working day.
The city’s construction inspector, Moe Omer, will be onsite regularly during construction and is available to answer questions. His contact information is momer@plymouthmn.gov or 763-509-5529.
No work will be done on Monday, Sept. 2 (Labor Day)
Mapledell Paving should be completed next week. Irrigation repairs are completed in this neighborhood. Please test your irrigation systems and call Moe if you are still having issues.
Heritage/Medicine Lake Highlands The contractor has completed paving this neighborhood (excluding Rosewood Lane). The contractor will be finishing punch list and warranty items over the next few weeks, including irrigation repairs.
Westridge Estates/Forster Preserve The contractor plans to complete the trail paving August 30. Irrigation repairs will continue as well. Milling of the neighborhood roads is anticipated to begin the week of September 9.
Nathan Lane, Schmidt Lake Road, 45th Avenue, Highway 169 Service Drive The contractor is planning to pave the first layer of asphalt on Schmidt Lake Road the week of September 3. Trail work will continue.
|