Birchwood Estates Reconstruction Project Update
Please note, all dates are weather dependent and subject to change. See the phasing map in the May Construction Guide for phasing illustration.
Phase A1 The week of July 29, the contractor will start grading the gravel to prepare for the first layer of asphalt. The first layer of asphalt is tentatively scheduled for July 31.
Phase A2 The week of July 29, the contractor plans to begin rebuilding the gravel section of the road.
The city’s construction inspector, Drew Bailey, will be onsite regularly during construction and is available to answer questions. His contact information is drew.bailey@bolton-menk.com or (763) 358-1045.
|
|
|
|