Construction Update July 19 - All Timelines Are Weather Dependent
Mapledell
The contractor will continue to pour new curb the week of July 22. Once complete, the contractor will do bituminous patching on the street side, and repair irrigation issues and place black dirt and seed on the vegetation side.
Heritage/Medicine Lake Highlands
The contractor will do utility work on Rosewood Lane early the week of July 22, and plans to start pouring new curb where curb removal has taken place. Newly poured curb takes 7 days to harden and should not be driven on during this time. Owners should park on the street and have cars out of the construction area during the working day.
Westridge Estates/Forster Preserve
The contractor will be grading 42nd Avenue the week of July 22 to prepare for possible paving on Saturday, July 27 (weather dependent).
Minor utility work is planned within the residential streets along Old Rockford Road the week of July 22.
Nathan Lane, Schmidt Lake Road, 45th Avenue, Hwy 169 Service Drive
The soils on Nathan Lane (between 45th Avenue and Schmidt Lake Road) were too wet to pave July 18. Staff are hoping for dry weather the week of July 22 so the soils harden to a level suitable for paving.
The contractor will continue to work on the new retaining wall on the south side of Schmidt Lake Road near the Highway 169 ramps. The eastbound lane closest to the Holiday gas station will be closed. One eastbound lane and the two westbound lanes on Schmidt Lake Road will remain open for the retaining wall construction.
The city’s construction inspector, Moe Omer, will be onsite regularly during construction and is available to answer questions. His contact information is momer@plymouthmn.gov or (763) 509-5529.
|