June 25 Construction Update
Private utilities companies continue to relocate their facilities along the corridor.
This week the contractor has been installing storm sewer at the 34th Avenue intersection (City Hall entrance). They also plan on installing watermain and storm sewer at the 35th Avenue intersection. Also this week, the grading crew will start constructing the road near 34th Avenue.
The week of July 1, the contractor will be installing storm sewer at the 36th Avenue intersection. They will also continue constructing the road near the 34th Avenue intersection and proceed towards the intersection with 35th Avenue. This schedule may change based on weather
The project is currently in Phase 1A of construction. Information on how to access key destinations and detour maps are available on the project webpage.
|
|
|
|