Construction Update June 14 - All Timelines Are Weather Dependent
Mapledell
Private utility work (CenterPoint, Xcel, Comcast, etc.) continues. CenterPoint has completed their mainline work and will continue connecting home services to the mainline for the next 2-3 weeks. These utilities are being relocated because they are either in the way of the city’s proposed infrastructure or because their maintenance cycles are in alignment with the project. This work will be primarily within the street right of way, however, there may be some work within side yard and backyard easements.
The city’s contractor for this project, Northwest Asphalt, is hoping to begin as soon as the private utility work is completed. While the contractor’s exact start date is still unknown, they will likely begin in late June.
Heritage/Medicine Lake Highlands
Private utility work continues. While the contractor's exact start day is still unknown, they will likely begin in July.
Westridge Estates/Forster Preserve
Private utility work continues. The city’s contractor for this project, Northwest Asphalt, is working on construction of the trail and curb on Old Rockford Road between Larch Lane and French Park.
Additionally, the contractor is planning to remove pavement and begin minor utility work on 42nd Avenue the week of June 17.
Nathan Lane, Schmidt Lake Road, 45th Avenue, Hwy 169 Service Drive
The contractor plans to remove pavement on Phase 1B (Nathan Lane between 45th Avenue and Rockford Road) on June 17. If road gravel work goes smoothly and the weather is favorable, they plan to pave Phase 1B on June 21.
The city’s construction inspector, Moe Omer, will be onsite regularly during construction and is available to answer questions. His contact information is momer@plymouthmn.gov or (763) 509-5529.
|