Construction Update - October 27
The Gleason Lake Drive and Vicksburg Lane intersection opened to traffic on September 1. Minor items remain to be completed. Other intersections along the project corridor will periodically be closed to allow for construction activities. The contractor will maintain access to owners in the area, but delays should be anticipated during construction work.
Phase 1A, 1B, and 2 – Kingsview Lane & Gleason Lake Drive between Vicksburg Lane and Niagara Lane The contractor is planning to put down the final layer of asphalt late next week.
Phase 3 - Gleason Lake Drive between Niagara Lane and Carlson Parkway The contractor is behind the original projected schedule. However, they are still expecting to have asphalt down this year. Earth and gravel work hs begun between Juneau Lane and Lanewood Lane, and will continue moving west of Lanewood Lane next week. Additionally, the contactor is planning to get curb down late next week as well.
The temporary access road to the Harbor Lane neighborhood will be needed several more times over the next month or so. While the temporary access road is in use, residents of the Harbor Lane neighborhood will only be able to enter/leave from Carlson Parkway, and only residents with direct driveways to Gleason Lake Drive will be able to access Gleason Lake Drive between Juneau Lane and Harbor Lane from the west. Additionally, access to Carlson Parkway will not be available at times when the contractor is working directly adjacent to Carlson Parkway. During these times, all residents will have access from Gleason Lake Drive.
We appreciate your patience as we work to complete this portion of the project as quickly and safely as possible.
|