 Construction Update - Oct. 6
The contractor is currently installing a retaining wall on Chankahda Trail near Maple Grove Parkway and taking delivery of the materials for the new box culvert at Elm Creek. Next week the contractor plans to remove the existing box culvert and start installation of the new box culvert. Seeding of areas east of Archer Lane is scheduled for next week and paving of the trails between Archer Lane and Inland Lane is tentatively scheduled for the end of next week.
|
|
|
|