Construction Update - October 6
Phase 2 (Nathan Lane, 56th Avenue, and Hwy 169 Service Drive north of 54th Avenue)
The contractor continued grading this week and prepared for the remaining gravel areas to be paved. Weather permitting, the contractor plans to continue paving this Saturday, October 7. Next week, paving will be finished throughout all of Phase 2, including the trail along Nathan Lane, and restoration behind the curb will begin.
The intersection at 56th Avenue and Nathan Lane is currently closed and will be until construction is complete at the realigned intersection. Access to businesses and residences in the Nathan Area north of 56th Avenue will remain open to traffic from Bass Lake Road. For businesses and residences south of 56th Avenue, access will remain open to traffic from Schmidt Lake Road. No vehicles will be able to pass through the intersection of 56th Avenue and Nathan Lane until further notice. Delays should be anticipated during construction with narrowed roadways and detours in and around the project area.
A project help line has been established for resident questions or concerns during construction; the help line number is (763) 331-8619. Alternatively, residents can contact the construction observer Arianna Christian at 612-398-8949, or project manager Nick Amatuccio at 612-965-3926 or email nickam@bolton-menk.com.
|
|
|
|