Construction Update - Sept. 29
Last week the contractor paved the initial layers of pavement on Chankahda Trail from Archer Lane to Inland Lane. Remaining work in this area includes paving of the trails, restoration, and other minor work. The contractor has removed pavement on Chankahda Trail west of Inland Lane and is constructing a retaining wall. Next week the contractor anticipates starting removal of the existing box culvert at Elm Creek.
|
|
|
|