September 15 Update: 2023 City Center Pavement Rehabilitation Project City of Plymouth, MN sent this bulletin at 09/15/2023 09:08 AM CDT Having trouble viewing this email? View it as a Web page. Street Project Update Construction Update September 15 Phases 2B and 2C – 36th Avenue and 37th AvenueThe final layer of asphalt has been paved and the project is substantially complete. The contractor will be completing the landscaping, striping, and signage later this week or early next week. PROJECT WEBPAGE