Construction Update September 8
Phase 2B update – 36th Avenue The contractor is scheduled to pave the final layer of asphalt today. Next week, the contractor will finish up the median landscaping and restore any disturbed turf areas. The roadway will remain open to traffic, but delays should be anticipated as the road may be reduced to one lane with flaggers.
Phase 2C update – 37th Avenue The contractor installed the asphalt trail this week. Next week, the contractor will pave the final layer of asphalt in the street and restore all disturbed turf areas. The roadway will remain open to traffic, but delays should be anticipated as the road may be reduced to one lane with flaggers.
|
|
|
|