Construction Update - September 1
Phase 2 (Nathan Lane, 56th Avenue, and Hwy 169 Service Drive north of 54th Avenue)
The contractor finished storm sewer installation and began street grading in Phase 2 this week. Next week the contractor will finish utility work with watermain improvements and removals at the intersection of Bass Lake Road and Nathan Lane. Later next week, the first layer of pavement will be installed in the areas that were graded this week. The intersection at 56th Avenue and Nathan Lane remains closed until construction is complete at the realigned intersection.
Access to businesses and residences in the Nathan Area north of 56th Avenue will remain open to traffic from Bass Lake Road. For businesses and residences south of 56th Avenue access will remain open to traffic from Schmidt Lake Road. No vehicles will be able to pass through the intersection of 56th Avenue and Nathan Lane until further notice. Delays should be anticipated during construction with narrowed roadways and detours in and around the project area.
A project help line has been established for resident questions or concerns during construction; the help line number is (763) 331-8619. Alternatively, residents can contact the construction observer Arianna Christian at 612-398-8949, or project manager Nick Amatuccio at 612-965-3926 or email nickam@bolton-menk.com.
|
|
|
|